Replies: 3 comments 2 replies
-
Yes you can tie one action to another. One way would be to combine several Managers into one with a number of days from one action to the next. |
Beta Was this translation helpful? Give feedback.
-
Hi, Here is the script:
|
Beta Was this translation helpful? Give feedback.
-
I think this is a working solution:
|
Beta Was this translation helpful? Give feedback.
-
Hi,
I have run some long-term simulations and the problem that I run into is that while using fixed dates for sowing and tillage one whole year can have a gap in harvest. For example, when harvest happen after the fixed date given for tillage. And although there must be a first date for the first sowing and tillage operations I was wondering if the subsequent tillage operations could be implemented as days after harvest (EndCrop), and the sowing could also be implemented as days after harvest (EndCrop) so I can fix it to happen right after the last tillage operation?
As always, thank you for the help!
Beta Was this translation helpful? Give feedback.