-
Notifications
You must be signed in to change notification settings - Fork 10
/
ORNL-1868.txt
2966 lines (1915 loc) · 62.3 KB
/
ORNL-1868.txt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
892
893
894
895
896
897
898
899
900
901
902
903
904
905
906
907
908
909
910
911
912
913
914
915
916
917
918
919
920
921
922
923
924
925
926
927
928
929
930
931
932
933
934
935
936
937
938
939
940
941
942
943
944
945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
ORNL-186 -
C-84 —~ Reaoctors-Special Featu i’o%‘?irfiaft Reactors
X
AEC RESEARCH AND DEVELOPMENT REPORT
LA
e |
l
bt 3 3 4456 034984Y 5
bl | 1V :
=z i) ]
&ry ' Yl
G\ o
H..J L\ N DISASSEMBLY AND POSTOPERATIVE EXAMINATION
‘-‘fl. i\ 1"
o vocn f ; ! f’.\,\i
D 0N OF THE AIRCRAFT REACTOR EXPERIMENT
Jesida s
dd i )1
Wy ’\: W. B. Cotirell
T. E. Crabtree
k:' : A. L. Davis
W. G. Piper
Cuss;rrc.wnm CHANGED To- D
it
BY AuthoriTy Op._
OAK RIDGE NATIONAL LABORATORY
operated by
UNION CARBIDE CORPORATION
for the
U.S5. ATOMIC ENERGY COMMISSION
ORNL-1868
C-84 — Reactors-Special Features of Aircraft Reactors
M-3679 (20th ed., Rev.)
This document consists of 50 pages.
Copy}m 273 copies. Series A,
Contract No. W-7405-eng-26
AIRCRAFT REACTOR ENGINEERING DIVISION
DISASSEMBLY AND POSTOPERATIVE EXAMINATION
OF THE AIRCRAFT REACTOR EXPERIMENT
W. B. Cottrell A, L. Davis
T. E. Crabtree W. G. Piper
DATE ISSUED
. S Py - i
F L
4 34 B e
AEE& T Adhder
OAK RIDGE NATIONAL LABORATORY
Ook Ridge, Tennessee
operated by
UNION CARBIDE CORPORATION
or the
U.5. ATOMIC ENERGY COMMISSION
MARTIN MARIETTA ENERGY SYSTEMS LIBRARI
- JITEEN T
3 4456 034984y 5
TABLE OF CONTENTS
IR OAUCHION o v oo sscno s s o ioims s nines e TS A TR R BT TR B e R e 1
Chronology from Final Scram to Disassembly. . o o v v vn e vin i ittt . 4
Disassembly of the Reactor and Auxiliary Systems. ..o vve ity 5
Auxiliary Shielding and Sofety Precautions « v v vvv v vn i vinn vib ke e b sows D
Dismantling of the Sodium System . .. v v vt vi vttt 5
Dismantling of the Fuel System. . . v v v v s i tnneiie sttt nnanann 8
Dismantling of the Reactor. v v v v v v v v v st s s i st ie ettt taatoenasnas 8
Dismantling of the Fill and Drain Tanks « o v v v vvvnvn vttt as 16
Somples Taken During Disassembly. v v oo v v i iin it 16
Results of Examinations of Samples . ... .. s o o AR BT B R e e B 21
Beryllium Oxide Blocks ..o vvin i ST, I o S B Pl AR, e 21
Structural Materials and Valve Components . . .. ..o v § W RS e R il i o wonces BB
Nonmetallic Materials + v v v v v v v v v e v v i v o v o S R e R T A SR R 34
Balanoid NalNEE o s susssis siasrs sinivre bipbu oo B 8055 3 KEA & Gen s sl s o s S oees e 34
Fuel Pump Pressure Transmitters . ... oo ey o ami e BT Bl ¥ A 38
Scale from Main Sodium PUmp v v v e v v s s v e annosnsrsssssrsnnssansonse D il 38
Activation Analyses of Sodium System Samples . .. ... . . i i i 39
Disposition of Fission-Product Activity « .o vvvueveniinininiiiiiiiniiniaeaen 39
Disposal of Disassembled System. . ..o v evvvvvn o B RN B IR R NS R PN e SISTOR. |
{
Tr
DISASSEMBLY AND POSTOPERATIVE EXAMINATION OF THE
AIRCRAFT REACTOR EXPERIMENT
W. B. Cottrell
T. E. Crabtree
A. L. Davis
W. G. Piper
INTRODUCTION
The Aircraft Reactor Experiment (ARE) was
successfully concluded in November of 1954,
and a detailed report of the operation was
published the following year.! At that time
it was thought that an extensive examination
of the reactor and system components after
disassembly was warranted. It was realized,
of course, that the level of radicactivity of the
I'#. B. Cottrell et al., Operation of the Aircraft
Reactor Experiment, ORNL-1845 (Aug. 22, 1955).
o
ey
/ STANOBY FUEL PUMP
components would necessitate extensive delays
in the examinations.
Since examination of a few critical ARE samples
showed nothing unexpected, much of the planned
hot-cell inspection was postponed and complete
examination of all but a few specimens was
indefinitely suspended. The few examinations
that were completed are described in this report,
along with a description of the disassembly of
the ARE system. Diagrams of the fuel system,
sodium system, and off-gas system are presented
in Figs. 1, 2,and 3 for reference use in visualizing
the disassembly process.
KEY:
X0 CROSS BARS ON LINES INDICATE WELDS,
ALL FUEL PIPE LINES NUMBERED iN 100 SEMIES.
Fig. 1. Diagram of ARE Fuel System.
UNCLASSIFIED
ORNL-LA-DWG 6245
P
P / STANDBY SODIUM
TQ g
|l'-;‘l
KEY:
L ©x=3 CROSS BARS ON LINES INDICATE WELDS.
o ALL SODIUM PIPE LINES NUMBERED IN
300 SERIES.
Fig. 2, Diagram of ARE Sodium System.
PRESSURE THANSMITTER
S0DiUM VAPDR TRAP
RESERVE TANK WO |
CARRIER FILL TANK NO. 2
Fig. 3. Diagram of ARE Off-Gas System.
CHRONOLOGY FROM FINAL SCRAM TO DISASSEMBLY
The nuclear operation of the ARE was con-
cluded at 8:04 PM, Friday, November 12, 1954,
upon insertion of the scram rods. Circulation
of the fuel and the sodium was continued, how-
ever, until the next day in order to allow the
afterheat to decay before dumping the fuel into
the fuel dump tank (and the sodium into the
sodium dump tanks).
During the period from shutdown of the reactor
until the fuel was dumped it was necessary for
the operating personnel to wear gas masks for
several hours because of the level of the airborne
activity. As was previously noted,' a gas leak,
which permitted gaseous fission-product activity
to be released to the cell, had existed ot least
since the start of high-power operation. The
exact location of this leak has never been de-
termined, although it was known to be from
the gas volume above the main fuel pump. While
it was subsequently shown that the diaphragm
of the main fuel pump pressure transmitter was
ruptured, it is believed that this occurred during
the early morning of November 13 and that prior
to that time the activity had been leaking from
one or more of the potential leaks in or around
the main fuel pump (spark plugs, seals, fill
lines, vent lines, etc,). In order to keep these
gases from leaking from the cell into occupied
areas of the building (the cell proved to be quite
porous), it was necessary to maintain the cell
at a subatmospheric pressure (-2 to —4 in. H,0)
by the use of a jet air pump which pumped around
100 cfm of air from the cell. This air, with its
activity, was discharged some 1000 ft south of
the ARE building,! but the negligible wind
velocity that existed at times during the period
after shutdown was not sufficient to cause
odequate dispersion of this activity. (Prior
to this period the wind had dispersed the activity.)
On the morning of Saturday, November 13, the
fuel was transferred into the fuel dump tank.
Since the fuel tubes in the reactor would not
have drained completely if the fuel had merely
been allowed to drain from the system by gravity,
the fuel was forced out of the system by pres-
surizing carrier material into one end of the
system and draining the other end of the system
into the dump tank. The fuel in the dump tank
was thus diluted by this flush material. The
dilution ratio was approximately 1 to 1.
In order to determine whether the fuel in all
six parallel reactor passages was removed,
the flush carrier was heaoted to a temperature
which was 100°F hotter than the fuel system
so that the pdssage of the carrier through each
of the six parallel reactor tubes could be ob-
served by thermocouples on these tubes. Although
the individual recorder charts showing temperature
differentials across each of the six reactor tubes
indicated that one tube (No. 4) did not clear,
the multipoint temperature record of all tubes
indicated that the carrier had passed through
all tubes. The individual temperature recorder
on tube No. 4 was subsequently found to be
inoperative.
After the fuel was dumped, the increased level
of the airborne activity caused all but a few
of the operating personnel who were wearing
gas masks to evacuate the building for about
1 hr. The gas used in pressuring the fuel system
during the dumping operation was discharged
to the stack, but the activity level in the building
rose because the wind at the time was such
that the activity descended and entered the
ventilators on the top of the building.
Following the completion of the removal of
the fuel on Saturday, November 13, the sodium
was drained into the sodium drain tanks. |In
this instance gravity drainage was sufficient
and was readily effected.
Evidence that all the fuel had been removed
from the reactor was obtained the following
Monday by a test in which the three control rods
were withdrawn from the reactor and no increase
in background count was observed. It was of
especial interest that there was no measurable
afterheat in the fuel; however, the expected
amount of afterheat was only o small fraction
of the electrical heat on the tank. Subsequent
analysis of the fuel indicated the activity to
be in reasonable agreement with expectations.
DISASSEMBLY OF THE REACTOR AND AUXILIARY SYSTEMS
The postoperative examination of the ARE system
started on December 10, 1954, with the taking of a
fuel sample from the dump tank while the fuel
was still molten. Disassembly of the reactor
and the auxiliary systems then proceeded os
radiation levels permitted. The primary objective
of this work was, of course, the obtaining of
samples for metallurgical, chemical, and physical
examination. It was also expected that in the
dismantling of the system much equipment could
be salvaged while the cells were being prepared
for the modifications required for the forthcoming
Aircraft Reactor Test.
Radiation surveys were used as a basis for
planning the disossembly sequence and techniques.
The radiation decay curves obtained from data
taken daily ot five monitoring points are shown
in Fig. 4.
AUXILIARY SHIELDING AND SAFETY
PRECAUTIONS
In order to separate the fuel circuit from the
sodium circuit for the purpose of dismantling
the sodium system, two flat lead shields, 6 ft
high, 4 ft wide, and 2 in. thick, were suspended
on beams which ran the width of the heat ex-
changer cell. For work in the higher radiation
fields associated with the fuel system, a leod
box was built that was 2 in. thick on four sides
and the bottom. One end of the bottom had a
6-in.-wide slot, and one side had an 8-in.-square
slot, 9 in. off the bottom, through which personnel
worked. The building crane was used for moving
the flat shields and the box.
In order to offset the fire hazard associated
with the sodium system, all water lines were
cut from the water manifold in the basement below
the heat exchanger cell, and no sodium lines
were cut with flame or arc torches. All sodium
lines were cut with hack sows, and all cut
lines were immediately sealed with several
layers of masking tape. Fire-fighting equipment
was available at all times.
DISMANTLING OF THE SODIUM SYSTEM
The work of dismantling the sodium system,
shown in Fig. 2, was started on Jonuary 18, 1955,
at which time the radiation level was down to
30 to 250 mr/hr with the lead shields hanging
between the sodium system and the fuel system.
The main sodium pump was removed first,
ond it was found that the rotary element had a
radiation reading of 12 mr/hr at contact with
the impeller. After the rotary assembly had
been cleaned in a bath of 50% kerosene and
50% methyl alcohol, the impeller was removed
and submitted for examination.
The standby sodium pump was removed as @
unit with 6-in. stubs left on all lines so that
the pump could be salvaged for use in other
experiments, At the time it was removed, this
pump, which had not operated during nuclear
operation of the reactor, had a radiation reading
of 1 mr/hr at contact with the bowl and the
top flange.
The sodium-to-helium and the helium-to-water
heat -exchangers were removed next. The water
that had remained in the heat exchangers was
first drained* into containers and removed from
the cell. The sodium lines were then cut with
a hand hack saw and the helium blower duct was
cut loose with a cutting torch. The exchangers
were thus removable as complete units. After
the insulation and electric heaters had been
stripped from the exchangers, neither showed
a radiation reading on the outside. The ends
of the cut sodium lines read 2 mr/hr ot contact.
After the removal of the sodium system pumps
and heat exchangers, it was found that the
radiation field had increased to about 600 mr/hr.
The equipment had helped to shield the area
from the fuel system radiation.
Sodium lines 304 through 309, 313, and 314
were then removed in as long lengths as possible
and sealed at the cut ends from air and moisture.
Valves in the lines were left as installed. Radi-
ation levels on these lines were 2 to 10 mr/hr.
During the removal of these sodium lines the
flat lead shields were adequate to protect
personnel from the radiation from the fuel system,
as shown in Fig. 5. The remainder of the sodium
piping ran adjacent to the fuel system, however,
and, in places, over and under the fuel piping,
and therefore the lead box described above had
to be brought into use. Sodium lines 301 and
302 were removed by personnel working within
the lead box. To moke the line cutting job
easier, the heavy gage stainless steel annulus
can surrounding the sodium line was cut by using
an electric arc before the sodium line was cut
e
ORNL~LR-DWG 27129
100
50
20 : \
10 e
-""'--.._
LOCATION OF MONITOR
RADIATION LEVEL (¢/hr)
AT CENTER OF SOUTHWEST SIDE OF THE HEAT EXCHANGER CELL
i- AT THE ELEVATION OF THE MAIN SODIUM PUMP.
» AT CENTER OF SOUTHEAST SIDE OF THE HEAT EXCHANGER CELL
5 - ABOVE THE STANDBY SODIUM PUMP.
3. AT SODIUM - TO- HELIUM HEAT EXCHANGER NUMBER 1 IN THE 2
" STANDBY SODIUM CIRCUIT.
4. AT THE CEILING OF THE NORTH END OF THE REACTOR CELL.
5 THREE FEET NORTH OF THE MAIN FUEL PUMP ON TOP OF LINE 19, .
"WHICH WAS THE EXIT LINE FROM THE STANDBY FUEL PUMP,
2y
2 ‘\
‘.'
N
",
' X
‘\:"‘
0_“
A
|..\‘ 3\
0.5 \-..—5\' <
..'\.\ \\.
e
l.§.' !‘-}
-‘I‘. E u — — 4
R
S 2
0.2 _—l
04 »
0 5 10 {45 20 25 30 35 40 45 50 55 60 65 70
DAYS AFTER NOVEMBER {2, 1954
Fig. 4. Radiation Decay Curves for Five Locations in ARE System.
LUINCL ASSIFIEL
PHOTO 14182
e — —
A )
" N T ]
Fig. 5. Heat Exchanger Pit After Removal of Sodium System Pumps and Heat Exchangers and Lines, Note lead shield used to protect workers from
fuel system radiation.
with a hack saw. The radiation level at the open
ends of lines 301 and 302, which were cut where
they entered the tank pit wall, was only 2 mr/hr,
but the radiation field in that region outside the
lead box was 700 to 1000 mr/hr.
Sodium lines 303 and 310, the lines to and
from the reactor, were removed next. Because
of the position of line 303, it was necessary
to sever it where it entered the reactor cell
The cutting
which was
wall by wusing an electric arc.
operation caused a sodium fire,
extinguished with Metal-X extinguishers. A small
amount of air activity, 2 divisions on the 2K
scale of the air monitor, was observed as o
consequence of the sodium fire. Both line 303
and line 310, which was cut with a hack saw
by a craftsman werking from the lead box, showed
radiation levels of 2 mr/hr at contact with the
ends of the lines.
Auxiliary equipment was removed as necessary
or convenient. Most of these items, such as
pump drive motors and lubricating oil systems,
were salvaged for further use. The radiation
level of the main sodium-pump lubricating system
was 2 mr/hr, but this was found to be surface
contamination. The oil showed no radiation,
DISMANTLING OF THE FUEL SYSTEM
A complete radiation survey of the fuel system,
made on February 14, 1955, showed 75 r/hr at
contact with the insulation on the rotameter of
the main fuel pump, 55 r/hr ot contact with
insulation on the dead leg on the bottom of the
pump bowl, and 12 r/hr ot contact with the top
flange. These high radiation levels indicated
the advisability of removing the high radiation
sources first, where possible.
The components of the fuel system are illus-
trated in Fig. 1, and a photograph of the cell
containing the fuel pumps is presented in Fig. 6.
The disassembly work was started with the
main fuel pump which was causing a high radiation
field. Removal of the rotary assembly caused
a small burst of air activity that cleared in 2
to 3 min. The radiation level of the rotary
assembly was 20 r/hr ot 5 ft. After removal
of the rotary assembly, the lines to the pump
were cut and sealed and the pump was lifted
out of the cell, as shown in Fig. 7. The radiation
level of the main fuel pump bow!l was 900 mr/hr
at 5 ft. The standby fuel pump was removed in
a similar manner. This pump was not used during
operation at power, and therefore the radiation
level on the bottom of the pump bowl was only
16 mr/hr. This pump was salvaged for further
use.
The fuel-to-helium and helium-to-water heat ex-
changers were removed next. The radiation levels
of both exchangers were 10 r/hr at 6 in. In order
to remove these exchangers intact, the water
lines and the helium ducts were cut. The electric
wiring which ran in large bundles across the
heat exchangers was removed by hooking onto
the bundles with the overhead crane and pulling
the wires out of the cell. The fuel lines to the
heat exchangers were cut by a craftsman working
from the lead box with a hack saw. The insulation
and the electric heaters were removed from the
heat exchangers after they were removed from
the cell, oand heat exchanger No. 2 then had
a radiation level of 10 r/hr at 12 in.
During removal of the pumps and heat ex-
changers, most of the fuel lines were cut at
one end., The open ends of these fuel lines
had radiation readings of 10 r/hr at 3 in.
Lines in the standby fuel circuit were free
of fuel and showed only surface contamination
of 2 mr/hr. The reactor supply and discharge
lines were cut with hack saws by craftsmen
working within the lead box. With the removal
of the fuel lines, all equipment installed in the
heat exchanger cell had been removed.
DISMANTLING OF THE REACTOR
On March 10, 1955, the concrete pit plugs were
removed from the top of the reactor pit and the
concrete blocks which lined the walls and bottom
of the reoctor cell were lifted out to provide
space for the lead box. A portable grinder with
a flexible shaft and an extension handle was
mounted on the side of the lead box. The crafts-
man could operate the grinder from inside the
box by using the extension handle.
The insulation was stripped from the reactor
and the sodium and fuel lines that were in the
reactor cell. The helium manifold and the control
rod chamber (Fig. 8) were then removed. The
helium manifold and the shim and regulating rod
chambers had radiation readings of 200 mr/hr
at contact.
The portable grinder was then used to cut
the fuel lines as close as possible to the reactor
can. These lines had radiation readings of
10 r/hr at 3 in. when removed. The grinding
- " UNCLASSIFIED
PHOTO 14191
e et 2 B
B
- T _ PP
Fig. 6. Heat Exchanger Pit Showing Components of Fuel System Before Dismantling Operation,
0l
Fig. 7. Main Fuel Pump Being Lifted from Cell.
UNCLASSIFIED
PHOTO 14205
€
T
.o 1 -"‘!'*T
HELIUM /
RETENTION TANK
VIEWING PORT—_ ||
MG
'~
\\\\\\\
xxxxx
Fig. 8. Diagram of Reactor.
UNCLASSIFIED
ORNL-LR—DWG 6221
SODIUM CUTLET
PRESSURE SHELL
THERMAL SHIELD
GAS TIGHT SHELL
SAFETY CHAMBER NQ. 2
MICROMICROAMMETER
-
LOG N METER
8F, CHAMBER AND
TEMPERATURE SERVO MECHANISM
SAFETY CHAMBER NO.{
11
operation generated so much heat that it was
necessary, as before, to cut the sodium lines
with a hack saw. The sodium lines had radiation
readings of 300 mr/hr at contact.
The gas-tight shell surrounding the reactor
was then cut in quarter sections by using an
The can had a radiation
electric arc (Fig. 9).
level of 200 mr/hr at contact. The exposed reactor
pressure shell showed 6 r/hr at 6 in.
Special disassembly tools were fabricated for
dismantling the reactor. This equipment included
a steel tank with driven rollers for rotating the
reactor and a hydraulic-powered cutoff grinder
with a 14-in.-dia abrasive wheel. The reactor
. L
’ PHOTO 14186
Fig. 9. Gas-Tight Shell Being Removed from Reactor.
12
is shown in Fig. 10 positioned in the tonk for
grinding, and the cutting side of the grinder,
which was designed to be used under liquid,
is shown in Fig. 11. With this equipment, a
period of five 8-hy days was required to cut
the 2-in.-thick pressure shell. Upon removal
of the shell,- a radiation check was made. The
top of the reactor showed a radiation level of
75 r/hr at contact and the side showed 37 r/hr.
The next task was the removal of fuel tubes
and samples of the BeQO moderator blocks. The
fuel tubes and the BeO blocks were encased
in a stainless steel can with welded seams,
shown in Fig. 12, and the small sodium tubes
A : PHOTO 14655
. ¥
L P
Fig. 10, Reactor Positioned in Disossembly Tank for Grinding.
13
I UNCLASSIFIED
- PHOTO 14659
Fig. 11. Cutting Side of Grinder for Dismantling the Reactor.
662
PHOT
— -
Fig. 12. Top of Reactor After Removal of Pressure Shell and Some of the Sodium and Fuel Tubes.
15
that penetrated the BeO blocks were welded to
the top and bottom of the can. In order to free
the top of the can, the welds holding the sodium
tubes were drilled out and the outer edge of
the can was cut. The reactor was then placed
in a horizontal position and the fuel tube bends
were cut off flush with the bottom of the can.
After removal of the bottom tube bends, the
reactor was set upright and the crane was used
to pull out the fuel tubes and to place them in
drums, as shown in Fig. 12.
With all the fuel tubes removed, only the BeO
blocks remained in the can. The required samples
of BeO were obtained, and the can containing
the BeO blocks was taken to the storage area.
The radiation reading at that time was 4.5 r/hr
at 2 ft. The reactor cell was then cleared of
all contaminated material left from disassembly
of the reactor.
DISMANTLING OF THE FILL AND DRAIN
TANKS
The fuel dump tank was removed first because
it presented the only radiation in the tank pit,
which also contained three sodium tanks and
three fuel-carrier tanks. (One of the fuel-carrier
tanks was not used.) A radiation survey showed
18 r/hr at contact with the top of the tank,
990 r/hr in one of the cooling tubes through
the tank, and 84 r/hr at contact with msulntwn
on the side of the tank.
In order to get the lead box into position
for disassembly work, it was necessary to remove
steel framework, o space cooler, and the stack