-
Notifications
You must be signed in to change notification settings - Fork 10
/
ORNL-CF-68-5-11.txt
1308 lines (712 loc) · 30.5 KB
/
ORNL-CF-68-5-11.txt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
892
893
894
895
896
897
898
899
900
901
902
903
904
905
906
907
908
909
910
911
912
913
914
915
916
917
918
919
920
921
922
923
924
925
926
927
928
929
930
931
932
933
934
935
936
937
938
939
940
941
942
943
944
945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
i
el
X-822
DATE:
SUBJECT:
TO:
FROM:
OAK RIDGE NATIONAL LABORATORY | - |
Operated by - - Internal Use ~Only
UNION CARBIDE NUCLEAR COMPANY S » )
~Division of Union Carbide Corporation | 0 R N L
= | CENTRAL FILES NUMBER
Post Office Box X | |
Oak Ridge, Tennessee o ' - | 68_5-—11
May 1, 1968 cory No. 4
»Performance of MSRE Nuclear Power COHbTOl System@
(MSRE Test Report 5.2.1)
Distribution
C. H;”@abbard»
ABSTRACT
The nuclear power control systems of the MSRE were evaguated
by observ1ng the steady -state opefatlon of the reactor and by
conducting a series of transient tests, The temperature servo
was found capable of controlling all the transients that were
1ntmoduced However, because of the relatively slow response
and inherent stability of the reactor system, the temperature
servo was found to be relatively inactive during many of the
load change transients, The automatic load control operated as
expected except that the minimum power &vallable to the auto-
matic control was about 2 Mw. 1nstead of 1 Mw as had been planned.
This has not caused a problem in the reactor operation because
the load control has normally been operated in "manual",
NOTICE
This document contains information of a preliminary nature
and was prepared primarily for internal use at the Oak Ridge
National Laboratory. It is subject to revision or correction
and therefore does not represent a final report. The information
is not to be abstracted, reprinted or otherwise given public
dissemination without the approval of the ORNL patent branch,
Legal and Information Control Department.
INTRODUCTION .
CONTENTS
TEMPERATURE SERVO CONTROL OF NUCLEAR_POWER .
oteady-State Performance . .
Normal Setpoint Change . . . v v ¢ « « .« .
- Rapid Load Changes
Temperature Setpoint Error.
Control by Negative Temperature Coefficient
At Reactivity
AUTOMATTC T.OAD CONTROL .
CONCLUSIONS. . . . . .
APPENDIX . . . . . .
O N U = = LQ
13
15
18
21
INTRODUCTTON
Two independent control systems are used to set and control the
‘nuclear power of the MSRE at power levels above 1 Mw. The heat removal
rate is set by the air flow conditions at the radiator. The temperature
servo con'trollerl then adjusts the control rods to match the nuclear
power with the heat removal rate while maintaining the reactor outlet
temperature constant at a preselected value. An automatic load control,Z
which increases or decreases the radiafior heat removal rate, is provided
for the convenience of the operators.
A test program for evaluating the performance of the‘temperature
servo and the automatic load contrcl was outlined in MSRE Test Memo 5.2.1,
The program for evaluating the temperature servo consisted of steady-state
performance at each power level as the reactor was initially brought to
full power and of transient tests at several»pOWér levels'after'steaéy-
state full-power operation had been satisfactorily demonstrated. |
Additional transient tests were performed with the rod control in
"Manual' to demonstrate the inherent self-regulating characteristics of
the reactor. The autdmatic load control was tested during both a load
increase and a load decrease.
TEMPERATURE SERVO CONTROL OF NUCLEAR POWER
Steady-State Performance
- The steédy~state evaluation of the temperature servo was based on
the degree of hunting by the regulating rod, cycling of the reactor power
or outlet temperature, and afiy long term drifts or cycling.
1J. R. Tallackson, MSRE Design and Operations Report, Part II-A,
Nuclear and Process Instrumentation, ORNL-TM-729, Part IT-A, Oak Ridge
National Laboratory, February 1968, p. 229.
- 2Tpbid., p. 30L.
With two exceptions the steady-state performance'of the temperature
servo has been excellent. Farly in the power operation of the reactor, a
daily cycle of 3 - 4°F occurred in the reactor outlet temperature as
measured by the computer and other instrumentation. ' The temperature
servo, however, indicated that the temperature was steady. This problem
was found to be the lack of room temperature compensation of.the thermo-
couple signals into the temperature servo controller, and the fluctuation
in the reactor temperature was the result of the day-to-night variation
in control room temperature. There has been no long term cycling or
drifting since the thermocouple compernsation was corrected, There was
cne period of erratic operation when there were oscillaticns in both the
power and the outlet temperature. This was corrected by the replacement
of a faulty operational amplifier in the controller.
- In all other respects the temperature servo has been completely
satisfactory. Adjustments in rod position are made rélatively infre—
quently and there are no cyclic fluctuations in the power or temperature
and no long term drifts in temperature. The steady-state performance
was originally to be documented by 15 minutes of fast scan data on the
computer each day during the approach to power, but this was discontinued
after the uneventful operation of the controller was observed.
Normal Setpoint Change
The first set of transient tests was changes in the reactor outlet
temperature by changing the temperature demand setpoint in the normal
manner, The temperature setpoint can be changed by moving a seléctor
switch to the "increase”’or "decrease" position until the desired tempera-
ture demand is feached, The setpoint is motor-driven at 5°F/min so that
the reactor»can follow the setpoint with about a 1-Mw power change. The
test program consisted of increaéing the temperature demand from 1210°F
to 1225°F, decreasing the demand to 1200°F, and then increasing the demand
to 1210°F. This test program was run at poWer levels of 1, 5, and T Mw.
The data was recorded on magnetic tape by the computer fast scan during
the transient, Appen&ix A lists the date, time period, and tape number
for each of the transient tests that was run. The results of a typical
setpoint transient are shown in Figure 1 which is a‘bomputér.plot of data
FHSTSCHN
PIGURE - 1 H e z==“!§"-355n PR ;iz: L !a*iifgks‘fa’-i i
i NORMAL SETPOINT CHANGE 1210 to 1225°F =’E=§“‘§si'§§3 HiH iiii!!fi ii E?&iiiii %iifiiiififi;!’#ifi i Lfiifixéfififl.fiifia?#fii gifiiixfifi i ‘Efii"d;-!-ii“ E!:’ i‘fig‘fgfii'! ;
H sl ot TNTTIAL POVER of 7 Mw HH ““ii!i,;?fifiii ""“EEE i BREREHE i "“'E!i!"=’i"i"“5”“"s§.‘f' i
R i - R nEtH sfi! fi% R §ii§!.§==5.s==E’Ei‘i‘=i=155!§u'ifis=s§‘=5§ifiaifii! Hii
i ik Eiil T T —— ...a,g...:;;;iii..xifl;‘mflfi ’i-Enmifi?fiE“fi?:é‘fiéfii’i“fiififi‘ifi e ii‘u‘ii‘éi !ain i
T : i i HHH ’3’::i5!=li"f_i5! L "?:‘=§__== := LR ii: =ii=-=i§i HHE i:l 3%‘:5 ::5! e 5::!:355 !ii!;I!.IiHEEEiE.-ii‘!iiiii iiii;_’ i §§§i=.§=!i'i§=ii‘=§ii" ‘3. -==!==.'i!!'5=! =ill‘ii'i'lgilggi!§§i‘=! i=§§!3=' Eii‘gl.iiggg'gié §§5§§=:= o
--------- o i i é;i.ii’..#i Iggf.auflfi.!?' i =.=z==5§'§555=§_= != T .fiiifiisizs"’!‘?fifii-fi‘ T ‘i‘:i.ainsiiaisgiigg.ai==s==s;= ;;sim
e fii‘“‘filfi‘afiifififi" ' “'iiiiifisi’ ‘ififiififi?? figfii: S 5,5 i
T .
mfifi!&sfl!éfifisfiim nfiéi s ,E’Eii .3 ’!’fiiiii'fi!i!i!i"i
i i E'M- i
fi“ififiifi’!fi fi;’!fi fig’fi. ';lgi [ :.. =.===. ====== :i::!!i!‘!
HH !i;li.... ,i!‘?ii"
i. |=.. '§§.: L '-=i§.,=§‘;!_s_=|!’§
’i‘aqa;
== ] “ EE ii m:E
=i§§g e ’==EEE"E‘:,:5’. | “ ;;i - fliagi:fi;, ;i% §I§ gég gnii‘i it
t e R
==...
=;;='= EiEEE T T T T i a.? s !=§i=sisaai?.fl"5=5 i _¥§= S i.!=5=! L HEmE it
i ”5’5‘4’“ §-§s§5’=§ i i B '35"‘3?5" i “?iifi’ii!i%fi' f’ifli!?!“?i i ’?hin‘ Efi‘ifi?“&%fifiififi L HEEIER R -:"‘Ei,!fi"fi:" *’u i :’?u’ifi’i i =‘5H” i E._E'.’... E'Eiflifli’ i i
i L BB e 'afi"ifi §§5§Ei!sa==§!i i ii’!is fiififi;fiifi" i ;iifiiiii. ;s ’Hfig’fi!fififiifi L ifi‘ifiii"'i iii.“%!iiifi‘i;sfifi‘fi'fi! e "ii.i’i o aii
i fi””“ el %ifiiiéfiiifififiif aiizi T i L E'hi'!!fl' e L ES‘ iy
I i -i.iii’;Egg, T %"" ’ “'fii ‘“‘Ffii Eifi“’ i !=isii§i¥:§ ==5E: isfii‘; 35” i ] ?Eiiiig? .fi‘ =§5§'i'EE’ig'gliifig"'“’-i:gi,g:fgé,fi, s i ] il ;gEE!!'-
| i gisflg&' R isiiii‘i}sfi;:figfi"iifi-fiil Hi EH i i Hi -i i
| :Z "fiflqfi_fi’fifi , ’fi% ii-i"fii’fiai“fl.i-”gs hfiifiiai%gfi;g E ’% fi”‘ flifi’ii iifiéi! ‘fi!flia?ifi!ii :fiifiifis B
ig r?fif:fi;?%fijgififfiiii i ;i‘: I sa= il ia Inggififnia‘fi;%:“ %?15335 ;;;i '; ififi g::igiiii‘i i;ii%giii ;’i{;fi; il %Efi'fi?fifigi E..ii 5 gfi:fi% i ='E " --‘ '5 '==5- -
i e =-=a§-:s!s;i§fl;a=sssaaaai,;:;-fi;hifi=-a: -%1‘5“ Efi‘i§= i ig L L aségfjifiéifii L ifii%igfi’&m e .
| o ii:i!giagifi?!‘“,fl:iiiii i fi’:: i fijfi iii%' @i’ iiii!fi !E!liiiliiiiiliifiiiifiuflilfifii hflgiiiisai"as: il figiiigh%ifiii ififi;fifi"‘fiéfi‘"’f‘"’fi!fiafi:fl i =E=§:' E;: =§-3g :E:ii::' s gé fig i
.‘ :’r i §.i=i§5' i,i‘iifigi'iihgifi!fii 5! ififi g ; Efii.ig’iffi! ififi i !fifs H ’ :==§ CTR ' :li! @fifi“ HHH ifiij!ii 5;%’ :i Elfi fl!’fli ::i% flgifiifii i‘!i-iéii!i iH e Hii! =E5’=§‘ !iiifi E; ii.'i =‘§lflifi!fil§§§
e e = ..
i m??wnamu I e ] !!; e R “*"”“’ L fifiiififiéfiifififiifi L i §= "Ei!ig'i ';E_'r:j-i' 'iii’m:'::;néi ;géii;:_nj-wfimw;”:
H Gl -E.:‘“' e ’::*:’!f.;!r.ni. HH
=!=a§=fiiiii§rr=5‘§§c§=-iis’i=a= ilsi;;. L§i=s§=§i§i“i e
E:igg niil;g:"" ":’Eilii i;?““-m‘?... !Jfi?ii EE“ isl E’i: CTOR nna aa H I’gl ;i EE;;.F’ fi:;”:;i.fi Efit?lgl QE
fi%@fi@g n%d%%fi?fii.fi*%myfi fifi%fi%@% m?fl %% %fifi
.:E ! HH H
R =====:'§ "§= ag =§ i: HE ] ".) i !! o ; §= f' :r l!!l = r! E“,fi!&:fl B '5“35 E‘mnimnigfiiilfiglw g ifi ST Ei‘:::::a:
..... mfifififfififififiwfifia' i h:%fi% i %fifigiw%fi%fifi%s%wfifwfi%fifiifis
i H H “":“ T T : 1» .. i H »_r S - HH 1 e Eiainfilg':; ’E'“ e T HHRh llfl' R
flffififi%f%flfi%fi%fifififiLfia_ a_“ fi’s@ . gfififi %%fifi%%fififi %hfirmééfififififififiafififiwfl
]
.
E%g%i i .giii“! =E“fii!:i a'mi"i": Y ijfl i
L E“i'niis. “=§'=5= i ‘ifi" i
==§§'55‘i =¥’!=5=, Efii'fiiiia i
e T
i She ""s; et e siain Gl
IR %iigka i i ‘fafifififig'fifii’d@"fi% e é; ifil!g.tga sii i
4 L i AN R fiiiéiissg ;3_;! ’!; ;Eég ‘:i:..ifi%iii’"i‘m,,_ o 553 gf;;*: i ,sfiiifiiz’:ii.iéfijgi
] @gwme. o mhflm@mm“'sfi#fififiWWW$mfifimmwfi%fifi#fiwflw_fifi%fifimi
%' Siai,;..'ididfli..i::iiaq i=“*=§.!& !iii i =’§§i=5'i’='E§!5§E=!§55'§i il ifi; i R i L
STARTING DATESs 1-29-67
%fifi_fi: fi""fi! *“*az-s'éfi?e =""-~
T
'f?*fimm%fififimfifififi%
si=i.=§aa.as§“§§5 e
4;@%g%fifi%§%,mmfid%mflmmfigfi
S i i:!“’:fl,: A i ‘:::"!iin’ NI T
:Elfliiigifl::l!:i _gé,:é;u;;;ggzs! g;';;“ !'5!;5: E;,::éi afi';i rfiliggiglii!“f;é?i ;Eg :Ei . fl.E:::i _4.}
. ;-’E,i'i"’ . . -
i 5=§==§§-’ iL, e e L ‘“iii“ii“iiii‘fiflfl'fi fifl
2HH T =§§
i =5’ "’ =si'iii§§!§ :::E'q's"i‘-i‘:iiifimiau*fi:‘ i iiii ‘Ei’m M EESH!
B
o
H
H
!
===G'-€"'
-
Efi”ifi'
H oo e =t
o 1 T
A% HH
R mgfi ]
Tt %EEE
..‘ E LT I..
-+ I
3
T
7 1
£ ,E_ELE;E;""
stored on magnetic tape by the MSRE on-line computer. Data was recorded
every 1/4 second during the tests in this report. The temperature set-
point was increased from 1210 to 1225°F at an initial power level of
about 7 Mw. The scattered points on some of the traces are computer
errors in reading the signal and are not actually changes in the par-
ticular signal. If the temperature demand setpoint were also plotted, it
would fall essentially on top of the reactor outlet temperature (TE-lOO~lA)
trace. The results of the other tests in this series were similar except
“for the temperature decrease from 1225 to 1200°F at a power level of 1 Mw.
In this test the;reactor outlet temperature could not track the setpoint
because a sufficient decrease in power was not available to pre&uce a
5°F/min temperature decrease., The control system cannot request a power
level below 500 kw so that a power decrease of only about 0.5 Mw was
available as compared to the 1-1/2-Mw increase which occurred during the
test plotted in Figure 1. This is not a deficiency in fihe control” system
since the only effect is a longer transient time in reaching the new
temperature.
Rapid Load Changes
The second sefies of transient tests consisted of making sudden
changes in the heat-removal‘rate at the radiator and observing the
reéponse.of the system as the temperature servo adjusted the reactor
power to matech the heat load. The following load changes were made:
1l Mw to 3 Mw
3 Mw to 5 Mw
5 Mw to 3 Mw
3 Mw to 7 Mw
T Mw to 5 Mw
| 5 Mw to Full Power (T7.22 Mw)
The results of the 3 - 7 Mw load change are shown on Figure 2., This
load change was made by changing the radiator settings as outlined below:
Nominal Power Inlet Door - Outlet Door Damper ‘Blowers On
3 30" ‘Upper Limit 100% open MB-1
T U.L. U.L. 50% MB-1 and 3
FASTSCAN
FIGURE - 2 ‘
STEP IOAD CHANGE 3 Mw to 7 Mw
in TEMPERATURE SERVO
STARTING DATEs 2 1 B7
STARTING DRTEs 2 1 b7
9
The load change was intended to be completed in about one minute, but in
practice, three minutes were taken to complete the change in radistor
settings. Although this load change was much slower than intended, it
was representative of the normal rate of increasing the power. The re-
actor power increased emdothly without oscillations or overshoot and there
was essentially no change in the reactor outlet temperature. The regu-
lating rod also showed little or no adjustment during the power transient.
The sine wave fluctuation on the regulating rod trace, and'also ch some
of the other traces during this and some of»the other tests, was some
type cf noise signal in the computer. The rod was actually more or less
stationary. The temperature servo could have made some,small corrections
in rod position that were masked by the superimposed sine wave. The
lack of regulating rod adjustment and the constant reactor outlet tempera-
ture indicated that the réactor is inherently stable and self regulating.
A similar, but more severe,'test was conducted when the autematic
"Load Control" was tested. The results of this test are shown on Fig. 6.
The temperature servo made only slight rod adjustments during this test
10 maintain a constant outlet temperatureo The power transient was
smooth without oscillations or overshocot.
Temperature Setpoint Error
The most severe transients were introduced into the reactor System
by switching from manual rod control to temperature servo control with a
mismatch between the actual reactor outlet temperature and the controller
setpoint., The servo controller immediately requests a power change in
‘proportion to the temperature mismatch to adjust the reactor outlet to
the setpoint temperature. The controller was restricted and could not
request power levels above 11 Mw or below 500 kw during these tests,
The upper limit has now been changed to 8.625 Mw to be consistent with
full-power operation at 7.5 rather than 10 Mw. The actual'response of
the reactor power is slowed somewhat by the rate at which the regulating
rod can be withdrawn and by the "rod withdraw inhibit" whieh limits the
reactor period to 25 seconds or greater. | | |
The following test program was used to evaluate the performance of
the controller in handling the relatively fast transients as the controller
10
corrected the temperature errors. This program was designed to test the
controller under a variety of conditions and also to test the limits of
500 kw and 11 Mw to see if these limits would be seriously exceeded. The
transient performance was recorded for temperature errors_ef + 5°F, + 15°F,
and + 25°F. These temperature transients were repeated at starting power
levels of 1, 5, and T Mw.
The results of the tests showed that the controller was more than
adequate to handle the transients that resulted. Figure 3-shows»the
response of the system during the most severe transient when.a +25°F
setpoint error was introduced at a power level of ~ 7 Mw., The initial
withdrawal of the_regulatingrrod was stopped several times by the 25-sec.
period "rod withdraw inhibit", The.power overshetfithe~ll-Mw limit
slightly (0.43 Mw) as the coumtrol rod was beingaiflserted to stop the
power increase, As the reactor temperature approgched the setpoint, the
reactor power was reduced relatively smoothly to the steady-state value,
The outlet temperature overshot the setpoint about 5°F. Figure L4 shows
the system response when a -25°F temperature error is introduced. The
reactor power was first reduced from ~ 7.1l Mw to ~ 1.5 Mw and then re-
turned to about the original value. The regulating rod was limited in
this case by the lower limit of its normal 6-inch range. If this physical
1imit on the rod motion had not stopped the rod insertion, the rod would
probably have been stopped by the "power less than 500 kw" limit. There
was 8 small overshoot as-the power was being increaSed_to the normal
operating point and there was a small undershoot in the reactor outlet
temperature at about the same time. The small smounts of overshocot and
undershoot shown in these tests were of no practical significance.
The tests conducted at ether power levels were similar to the ones
shown and the only difference was an increased tendency to oscillate at
the 1-Mw power level, However the'oscillations.in power and temperature
were small and were satisfactorily damped in all cases. The overshoot
or undershoot in the»temperature and,powerwere-damped out during the
first cycle for the tests at 5 and T Mw. There was no overshoot or
undershoot for any of the tests with a setpoint error of + 5°F.
FASTSCAN
FIGURE - 3
SETPOINT ERROR OF +25°F at INITIAL POWER of T Mw
STARTINC DBATESs
2
1
67
T
FASTSCAN
FIGURE ~ b
SETPOINT ERROR OF -25°F at INITIAL POWER of T Mw
STARTING DATEs 2- 1 67
cl
13
Control by Negative Temperature Coefficient at Reactivitz
After the above testing of the temperature servo controller was com-
‘pleted, a series of.tests was conducted to demonstrate the inherent con-
trol characteristics of the MSRE. The stability analySiS3 and the dynamics
testing4 that were completed previously showed that the system was stable
under all operating conditions and that the system would’be'self-regulating.
However, no previous tests had been run to demonstrate the system response
to sudden load changes. The following test program was conducted with the
load changes being made as quickly as was practical.
| Fullflpower to 4k Mw
L Mw to 2 Mw
2 Mw to 4 Mw
L Mw to 6 Mw
6 Mw to Full power
4 Mw to Full power
2 Mw to Full power
Figure 5 shows the results of the final test when the radiator heat
load was increased from.~ 2 Mw to full power in about 50 sec. with no
control rod movement., As can be seen in the plot there was a smooth
increase in power with no tendency to overshoot or oscillate. The re-
actor outlet temperature remained essentially constant except that there
was about a 2°F loss in temperature at about 150 seconds which recovered
‘about one minute later. The chenge in the rate of power increase occurred
at about the same time as the minimum reactor outlet temperature. The
other tests in the series were similar in having a smooth power trace
without overshoot or oscillation and having a constant reactor outlet
temperature. The 2°F dip in the reactor outlet temperature mentioned
above was not present in the other tests. Some of the early ana.log
studies on the MSRELhad indicated oscillations in the nuclear power and
°S. J. Ball and T. W. Kerlin, Stability Analysis of the Molten-Salt
Reactor Experiment, ORNL-TM-10T70, Oak Ridge National Iaboratory, Dec. 1965.
4T, W. Kerlin and S. J. Ball, Experimental Dynamic Analysis of the
‘Molten-Salt Reactor Experiment, ORNL T™- l6h7, Oak Ridge National
Leboratory, October 13, 1966.
TEMPERATURE (°F)
1k
ORNL—DWG 68—964
15
=z
3 10
& | REACTOR POWER
= - -
2 5 //
//
0
1250
REACTOR OUTLET
-
1200 —] |
\\ REACTOR INLET
M50 ‘\\\\
| \ RADIATOR INLET
. ‘\\\\\ — ]
1050 RADIATOR OUTLET
1000 \ —
0 40 80 120 160 200 240 280 320
TIME (sec)
Figure 5. Step Load Change 2 - 7 Mw with No Control Rod Motion.
15
in the various system temperatures especlally at low-power levels,
However, there were no indications of oscillations in any of the tests
listed above. |
This series of tests demonstrated the self-regulating characteristics
and the stability of the system under transient ioad conditions. The
main difference between the step load changes with the servo and without
the servo was‘that the initial change in power was faster when the servo
was used. The.servo made only a few rod adjustments after the first
portion of the transient. The nearly constant reactor outlet temperature
at the various power levels indicates that the nuclear average temperature
of the reactor is about equal to the fuel out let temperature and confirms
the very low power coefficient of reactivity (based on reactor outlet
temperature) that had been reported previously.>
AUTOMATIC LOAD CONTROL
The Automatic T.oad Control on the MSRE provides a method of in-
creasing or decreasing the radiator heat removal rate. The load control
either increases or decreases the load in a preselected sequence and it
does not actually control the load at a given level. The automatic load
control was designed for use at power levels greater than 1 Mw, and a
radiator door setting was to be specified with one main blower in opera-
tion to provide a starting point at 1 Mw of heat remOval. However, the
heat removal was about 1.9 Mw with the radiator doors at their minimum
open setting of 12 inches. The test during a power increase was started
from this point, but the power could not be lowered below ~ 3 Mw when
the load was decreased because the radiator doors were stopped at 50 in.
by the interlock switches.
The results of the load control test are shown on Figure 6. The
regulating rod position was not included on this plot because of a
S0ak Ridge National Laboratory, MSRP Semiann Progr. Rept. August 31,
1966, USAEC Report ORNL-L4037, p. 11.
FIGURE - 6
PERFORMANCE OF AUTOMATIC LOAD CONTROL
STARTING DATEs 9-21 67
17
relatively large low-frequenoy noise signal that existed in the computer.
No rod motion could be detected from the computer fast scan data during
this test. However in an earlier test, the rod was withdrawn about
0.9 inches at the beginning of the power'transient and was reinserted
to about the original position after about 30 - LO seconds. As can be
seen in the plot the power and temperatures are smooth without overshoot
or oscillation. -
The time sequence of the various control actions taken by the auto-
matic load control are given in Table T.
Table T
. | | | | | Computer
Action Time
1., ILoad Switech to "Increase'" — Radiator Doors start :
| | to raise S 1159:00
2. TRadiator Doors at upper limit — Bypass Damper started —
to close - 1159:28
3. Bypass Damper closed — Automatic Main Blower energized -1200:02
k. Bypass Damper partially open —-starts to reclose 1200:30
5. Bypass Damper fully closed | 1200:58
6. Reactor at full power | 1204 :00
T. Load Switch to "Decrease'" — Bypass Damper starts
to open - 1208 :24
Bypass Damper open — Automatic Blower deenergized 11209:00
9. Bypass Damper starts to close — Radiator Doors close
| - slightly 1209:10
10, Bypass Damper partially-closed'é-begins to open 1209:18
11. Bypass Damper open — Doors start to close 1209:35
12. Doors at intermediate limit | 1209:52
13, Reactor at minimum power_by automatic load decrease | 1213:00
‘The closure of the radiator doors at Step 9 had not been planned at
this point; However, the interlock conditions were.satisfied at this
time when the damper was open and the automatic blower was off. This
~problem was not serious and could be easily corrected by adding the
18
appropriate interlocks. As soon as the damper élosed'slightly,,the
lowering of the doors was stopped until the damper again reached the full
| open position. At this time the doors were lowered to their intermediate
limit as had been intended. The only other fault noted was that the
minimum power available to the sutomatic load control is abdve the transfer
point from Start to Run Mode. The bypass damper was also too slow to
follow the acceleration of the main blower, but this has no practical
significance. |
| Test Memo 5.2.1 outlined a series of tests in which the automatic
load control was to be used to increase and decrease the reactor power
in 1/2-MM'steps to determine any discontinulties in loading curve, These
tests were not conducted because the heat load at various radiator
\éettings had been previously determined. Figure 7 shows the performance
of the radiator at various settings. The heat load using the automatic
load control would follow the solid curves. There is a small gap,inhthe
heat-load curve at about 6 Mw when the second blower is energized,
However, this gap can be covered by manually adjusting the doors,
CONCLUSIONS
- The performance of the temperature servo has been excellent except
for the two cases mentioned earlier in this report. The servo adequately
controlled all the transients that were introduced with a minimum of
overshoot and oscillation,. In normal operation of the reactor, the
temperature servo is not called upon to control rapid transients because
of the relatively slow response and.fhe inherent stability of the system.
When operating at steady conditions, rod adjustments are made infrequently
and a steady power level is maintained by the inherent self-regulating
characteristics of the reactor. | o
The automatiec load céntrol performed generally as expectéd except
that the door settings for 1-Mw operation were below the drop point when
one blower was operated. If the intenmediate 1imit switches were set
at the minimum position, the reactor power would be about 2 Mw. This
DAMPER POSITION (% CLOSED)
DOORS OPEN
LOAD SETTING
DOOR POSITION (%% OPEN)
DAMPER OPEN
19
ORNL-DWG 67-4763
.
»
100
@
o
Sy
\~\‘
[ / /
1 | | A/ /'/
/