-
Notifications
You must be signed in to change notification settings - Fork 10
/
ORNL-TM-0522.txt
7590 lines (3447 loc) · 114 KB
/
ORNL-TM-0522.txt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
892
893
894
895
896
897
898
899
900
901
902
903
904
905
906
907
908
909
910
911
912
913
914
915
916
917
918
919
920
921
922
923
924
925
926
927
928
929
930
931
932
933
934
935
936
937
938
939
940
941
942
943
944
945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
OAK RIDGE NATIONAL LABORATORY
operated by
~ {osimite Price s~ UNION CARBIDE CORPORATION m
. Mic™glm Price $ L for the
s . U.S. ATOMIC ENERGY COMMISSION
Available fro
. Office ofg®Echnical jces . |
' De ent of Commerce ORNL- TM~- 522
ington 25, D. C. : E A
ashington ?fl&g}‘ s COPY NO. - 6‘5—‘
"
DATE - October 10, 1962
DESIGN STUDIES AND COST ESTIMATES OF TWO FLUORIDE VOIATILITY PIANTS
W. L. Carter, R. P. Milford, and W. G. Stockdale
ABSTRACT
Design studies and cost estimates were made for two on-site, fluoride vola-
tility processing plants. Each plant was assumed to be processing continu-
ously irradiated LiF-BeFs-ThF4-UF4 fuel from a one-region Molten Salt Con-
verter Reactor (MSCR) capable of producing 1000 Mwe (ca. 2500 Mwt). One
plant processed fuel at a rate of 1.2 fts/day, the second at 12 fta/day.
The smaller plant was designed and cost estimated for two processing con-
ditions: (1) retention of the waste salt for Pa-233 decay and recovery by
a second fluorination, and (2) discard of all Pa-233 as waste after the
-~ first fluorination. The larger plant was considered only for the case of
Pa-233 decay and recovery. The following capital and direct operating
charges were estimated:
Capital Cost Operating Cost
1.2 £t3/day Plant with
Pa-233 Recovery 12,556,000 1,103,000
12 :E"bs/de.y Plant with '
Pa-233 Recovery 25,750,000 2,241,000
1.2 £t3/3day Plant with
Pa-233 Discard 10,188,000
The chemical processing scheme consisted of volatilizing uranium as UFg by
treating the molten salt with elemental fluorine at about 550°C. The hexa-
fluoride was then collected by absorption on NaF and condensation in cold
traps, reduced to UF4 in a Ha-Fp flame, dissolved in make-up salt, and re-
cycled to the reactor. Make-up fuel was supplied by purchasing fully en-
riched J-235. The 1Li, Be and Th components of the fuel were discarded with
fission product waste.
NOTICE
This document contains information of a preliminary nature and wos prepared
primarily for internal use at the Oak Ridge National Laboratory. It is subject
to revision or correction and therefore does not represent a final report, The
information is not to be abstrocted, reprinted or otherwise given public dis-
semination without the approval of the ORNL patent branch, Legei ond Iinfor-
matian Control Department,
E’* —— T =
E‘ | 2
R =
E .
i
o
: \ ?
i
L‘EG_AL NOTICE
This report was prepared as an mccount of Gonmment sponsond worl: Neither the Uniteé S!uus,
nor the Commission, nor any person acting on behaolf of the Commission:
A. Mokes sny warranty or representation, expressed or implied, with respect to the eccurecy,'
eomplotoneu, or usefulness of the information contained in this report, or thot the use of
ony information, epperotus, mofhnd ‘or process disclossd in thll ropofl may ot infringe
privately owned rights; or ) _
B. Assumes any liabilities with respsct to fln vse of, or for damoges usolflng from |Iu use of
any informotion, apparatus, method, or process disclosed in this repart. .
As used in the above, “person acting on behalf of the Commission® Inelndcs any. cmployoe ot
contractor of the Commission, or employes of such contractor, to the extent thot such amployee
or controctor of the Commission, er- -employes of such contractor _prepares, disseminates, or’ _ ) ‘
provides access to, ony information pursuant 1o his employment or contract with the Commiufon, 7 7 7 - -
or his employment with such contractor. = - ‘ ‘ P o *
e g R S s e
-
e e e A Ao 1 o B S
(' 0 A\ b
it 1
’
1.0
2.0
3.0
4.0
CONTENTS
ABSTRACT
SUMMARY
INTRODUCTION
2.1
2.2
Reactor Description
Design Bases
PROCESSING MOLTEN FILUCRIDE SALTS
3.1
3.2
33
3.1
3.5
3.6
Pre-Fluorination Storage
Flucrination
Waste Storage
Na¥ Absorption
Cold Trap
Reduction and Fuel Make=-up
PROCESSING PIANT DESIGN
L.l
h.2
k.3
bl
4.5
Decay Heat Removal
Equipment Design
Prefluorination Storage Tanks
Fluorinator
CRP Trap and Abscrbers
Cold Traps
Reduction Reactor
Fuel Make-up
Pa-233 Decay Storage System
Interim Waste Storage Tanks
Freeze Valves
Line Heating
Samplers
Refrigeration
Shielding Calculations
Source Strength
Geometry
Process Equipment Layout
Plant Layout
Site locaticon
o
o
OO0 W
®
CONTENTS ~- contd
1.5 Over-all Plant layout
5.0
6.0
7.0
Processing Area
Pa-233 Decay Storage
Waste Storage
Crane Maintenance Area
Contaminated Equipment Storage
Decontamination Cell
Canyon Shop
Railrocad Dock
Control Room
Sample Gallery
Iaboratories
Offices
Service Areas
CAPITAL COST ESTIMATE
5.1 Accounting Procedure
5.2 Bases of Estimates
Process Equipnment
Building
5.3 Process Equipment Capital Cost
5.4 Building Capital Cost
5.5 Total Capital Cost
OPERATING COST ESTIMATE
6.1 Operating Manpower
6.2 Summary of Direct Operating Costs
CAPITAL COST ESTIMATE OF MODIFIED
1.2 Fr3/DAY PIANT
T.1 Modifications
7.2 Process Equipment
T.3 Waste Storage
7.4 Process Building
7.5 Total Plant Cost
7.6 Economic Advantage
6L
6L
65
65
66
66
70
1.0 SUMMARY
Capital cost and operating cost estimates have been prepared for two
on-site fluoride volatility processing plants. The respective plants are
designed to treat 1.2 and 12 £t3/day of an irradisted LiF-BeF,,~ThF) -UF,,
fuel from a Molten Salt Converter Reactor (MSCR) which has a conversion
ratio of about 0.8. The uranium-free fuel has the compcsition 68-23-9
mole % LiFmBngwThFh; approximately 0.66 mole % UF& is required for crit-
icality in the equilibrium reactor.
The assumed reacztor and chemical processing plant environment is a
1000 Mwe (ca. 2500 Mwt) central power station. This power is generated
in a single reactor which is 15 ft in diameter by 15 ft high. The one-
region system is 90 vol % graphite and 10 vol % fuel contained in an
INOR-8 shell. Heat is removed by circulating the molten fuel salt through
the core and external heat exchangers at an average temperature of approx-
imately 1200°F. Spent fuel is removed semi-continuously every 3-5 days
for reprocessing; make-up fuel (U-235 + Th) is added on the same schedule.
Total fuel volume is 1780 fts,
The chemical reprccessing plant utilizes fluoride volatility to re-
cover decontaminated uranium. Neither thorium nor the carrier salt
(1IiF + BeFe) is recovered; both are discarded as waste with the accom-
ranying fission products. In one phase of this study the waste salt was
retained 135-175 days to allow Pa-233 decay and recovery by a second
fluosrination. In a second phase of this study protactinium was discarded
with the waste salt immediately after fluorinstion. After fluorinationm,
all of the recovered UFE is burned in a Hg”Fé flame for reduction to UF#
which is dissolved in make-up IiF-BeF2=ThEu and returned to the reactor.
Make-up uranium (U-235) is also added at this point.
The accuracy and confidence level of any cost estimate depends upon
the amount of design detail. In this study all of the process operations
were considered in enough detail for preliminary designs of vessels and
equipment; complex vessels were considered mcre carefully to permit more
reliable cost estimation. The process building was laid out for conven-
ience of process operations and maintenance and was patterned after de-
signs of cother remctely operated plantsl that are the products of several
years experience and study. Cognizance was taken of the fact that the
reactor and chemical plant are an integral operation and can share cer-
tain facilities.
The treatment of protactinium in this study was made in the two
ways mentioned above to determine if there were sufficient value in the
protactinium to justify its recovery from the waste. The capital cost
cf the 1.2 ft3/day plant was estimated for the cases of complete Pa-233
discard and for Pa retention until the undecayed Pa amounted to only
0.1% of the bred uranium. The economics favored complete Pa discard
since considerable process equipment and building space were required
for this "dead" storage. A more complete evaluation of the process might
reveal that more favorable economics result from & nominal extension of
the prefluorination storage period allowing more Pa-233 decay at this
point. Increased process equipment, building and inventory charges would
have to be compared with the value of additional Pa recovery. This lat-
ter analysis was not made in this study.
The estimated capital costs cf the two fluoride volatility plants
are $12,556,000 and $25.750,000, respectively, for the 1.2 ft3/day and
12 ft3/day plants for the case in which the waste is retained for Pa-233
decay and recovery. For the case of complete Pa-233 discard, a capital
cecst of $10.188,000 was estimated fer the 1.2 fts/flay plant. A summary
¢f the ccst data is given in Table 1.1, and these same data are plotted
in Fig. 1.1, 1In drawing the curve, 1t is assumed that the cost data can
be represented by a straight line on a log-log plot. The slope of this
curve is 0,312 which may be compared with a value of 0.6 that is custom-
arily associated with a capital cest vs capacity curve for a chemical
plant. The lower value fcor the slope suggests that more favorable re-
processing economics will be realized with large processing plants.
irect cperating costs for each of the plants employing Pa recovery
were calculated and are summarized in Table 1.2. The labor charges corre-
spond te 104 employees for the 1.2 ft3/day plant and 133 for the 12 ft3/day
plant. It is of interest to note the relationship between operating and
capital costs for each of the plants. When the operating cost is divided
by the corresponding capital investment; the operating charge rate be-
comes 8.77%/year and 8.61%/year for the 1.2 and 12 ft3/day capacities,
respectively. These charges may be compared to a value of 15%/year that
has been found to be generally applicable in the chemical industry.
In the analysis of the 1.2 fts/day plant employing Pa-233 discard,
the on=-site, interim waste storage time was optimized. The optimization
was carried cut by considering cn-site storage costs versus salt mine
permanent storage ccsts as a function of the age of the waste salt. The
lowest tctal storage cost appeared to cccur for an on-site holdup of about
1100 days hefcre shipping toe permanent storage.
Table 1l.1.
Total Installed Equipment and
Building Cost
General Construction Overhead (22%
of Total Installed Equipment and
Building Cost)
Total Construction Cost
Architect Engineering and Inspection
(15% of Total Construction Cost)
Subtotal Project Cost
Contingency (20% of Subtotal Project
Cost)
Total Project Cost
Summary of Capital Costs for On-Site,
Fluoride Volatility Plants
1.2 ft3/Day Plant
12 ft3/bay Plant
with Pa-233 with Pa-=233
Recovery Recovery
7,458,100 15,294,700
1,640,800 3,36k4,800
9,098,900 18,659,500
1,364,800 25,798,900
10,h33,700 21, ;400
2,092,300 _4,291,300
12,556,000 25,750,000
1.2 ft3/nay Plant
with Pa-233
Discard
6,052,000
1,331,000
7,383,000
1,107,000
8,590,000
1,698,000
10,188,000
Table 1.2. Summary of Direct Operating Costs for
Two Fluoride Volatility Plants
Chemical Consumption
Utilities
Iabor
Maintenance Materials
Total Direct Operating Cost
Ratio of Operating Cost:
Capital Cost
Cost ($/year)
1.2 £t5/da 12 £t /aay
10,340 68,950
34,930 185, 500
757,200 900,300
300,100 1,085,800
1,102,600 2,240,600
8.77 %/yr 8.61 %/yr
UNCLASSIFIED
ORNL-LR-DWG 74109
CAPITAL. COST, Million &
0.1 1.0 10.0 10t
PLANT CAPACITY, Ft?® Sait/ Day
Fig. 1.1 Fluoride Volatility Processing Plant Cost for an On-Site Facility to Process MSCR Fuel.
.o\
2.0 INTRODUCTION
The utilization of thorium as a reactor fuel is being investigated
in several reactor systems which show promise of having a breeding ratio
greater than unity or at least a high conversion ratio, that is, a
conpversion ratio greater than about 0.5. This report covers that portion
of a study concerned with processirg spent molten fluoride salt from a
one-region, converter reactor for recovery of decontaminated uranium,
It is the purpose of this study to develop capital cost data for fluoride
volatility processing plants capable of processing 1.2 and 12 ftB/day cf
A
nolten fluoride fuel,
2.1 Reactor Description
The reactor for which the chemical plant has been designed is
fueled with a molten salt mixture that is basically 68-23-9 mcle %
LiF-BeF,-ThF) containing sufficient UFy, ca. 0.66 mole %, to maintain
criticality. The reactor is a one-region assembly whose core has the
approximate composition of 10 vol % fuel solution and 90 vol % graphite;
the geometry is a right circular cylinder about 15 £t diameter by 15 ft
high. Fission energy is removed by circulating the fuel solution through
the core and an intermediate heat exchanger which is cooled by a barren.
salt solution. The barren salt in turn dissipates the heat in a steam
generator which produces 1000CF steam at 2000 psia. The average reactor
temperature is 1200%F.
The assumed enviromment for the reactor is that of a central,
power-producing facility generating 1000 Mwe at a thermodynamic efficiency
of approximately 42.3%. This load is committed to one reactor supplying
steam to two turbo-generator sets. The calculated fuel volume for the
station is 1780 ft3. The total uranium inventory, which includes all
isotopes from U-233 to U~258, is about 4200 kg; of this total the
fissionable component, U-233 + U-235, is in the range 2627 to 2815 kg
depending upon the processing rate. In addition the system contains
52,000 kg Th and 90.7-96 kg Pa-233. For this study it was assumed that
the system had a nowinal conversion ratio of 0.8, the remainder of the
fuel being supplied by purchase of fully enriched U-235.
10
2.2 Design Bases
In any study of this type the accuracy and confidence level of the
results depends upon the amount of design detail. More or less arbitrary
design bases were established to govern the extent of the study and to
augment those design conditions which were more firmly established. In
this respect the following rules were follcowed:
l.
The chemical processing plant and reactor power station would
be an integrated facility; i.e., on-site processing.
The design would be based as much as possible on existing tech-
nology; extrapolation of technology would be done only when
absolutely necessary.
A cost estimate would be made for each of two plants~-one
processing fuel at a rate corresponding to an estimated optimum
reactor cycle time, and a second processing fuel at an estimated
minimum reactor cycle time. These two estimates would then be
uged to determine processing costs at other processing rates by
interpolation or extrapolation. In doing this it would be
assumed that the capital cost versus throughput data could be
represented by a straight line on a log-log plot. For this
study the processing rates were 1.2 and 12 f£t°/day of fuel
containing respectively 2.83 and 28.3 kg U/day.
The fluoride vaolatility process would be used to recover
uranium which would be returned in tofo to the reac%or. No
thorium or LiF-BeF2 carrier salt would be recovered but would
be discarded as waste with the accompanying fission products.
This was a necessary decision because no developed process
exists for separating LiF-BeFp-ThF) salt from fission products.
The waste salt, which contains Pa=-233, would be held for Pa
decay and recovery until the undecayed Pa amounted to only
about 0.1% of the bred U~233. rAfter the second fluorination,
waste salt would be held 1000 days for fission product decéy
before transport to permenent waste storage. (See Section 7.0
for a modification of this basis.)
9)
ak
“)
+)
6. pThe.chemical'processingplant would share certaih facilities
- with the reactor plant, Teley cooling water, potable water,
stack, electrical services, steam, compressed air, storm and
| sanitary sewers, railroad and barge docks, shipping and
.receiving facilities, etc. These services were assumed avall-
able from the reactor site. The chemical plent bore the cost
of extending the services and, in the case of the stack, bore
the cost of increasing the stack size.
T. The extent of the design would be that which'completely defined
the process to ‘the point of having & preliminary design on all
-major process equipment. Building and auxiliary service space
would be determined in the light of biologleal shield require-
'ments and accepted operating practices for a remotely maintained .
radiochemical plant._ In this regard experience and studiesl’
on the Savannah River type plant were referred to for design of
several areas of the building.
3.0 PROCESSINGMOL‘I‘EN_ FLUORIDE SALTS
The fluoride volatility;plant:for processing the irradiated fuel
'}is'assumed‘to be lcceted adjacent to the reector area so that fuel trensfer
"cen be made by apprOpriately heated,pipe lines. Inside the chemical plant
the process operations are carried out according to the flcwsheets of
Figs. 3.1 and 3.2 for the 1.2 and 12 ft3/day plants, respectively. The
"two flowsheets are quite similar and incorpcrate the same process steps.
VVL There are slight differenoes, however, brought about by the quantity
| f;{%of fuel handled and- size of process equipment, for example, in preflor-
rffggination storage and. Pa-233 decay storage.
The fuel solution is & rather camplex mixture cf mol ten fluoride '
f'ftsalts of fertile, fissionable, end fissicn product nuclides. The major
:i-icqmponents are LiF, BeF2, ThFu, UFu, ‘and, Pth. —'r*",,.;p o
31 Prefluorination Storage -
Extremely radioactive fuel solution, which will be only a few
. minutes old, must be allowed to decay before fluorination to preclude -
UNCLASSIFIED
kg/d
Uy = 0.537 .
U, = fimiongble vranlum
Th o 2,08 FISSION U: = totgl uronfum (includes fasionable and : - ORNL-LR-DWG £3505
non-fisslonabie 'P'c'.l) pm—— NGF = 5,2 ltg/d —II-—NOF w52 l(fl/d
REACTOR kp/d ke/d _
SYSTEM U, = 1,898 U = 1904 d d
P = 2500 Mwt u: = 2.831 : U: = 2,838 Y : EL v kg/d
V = 1780 #3 Pa = 0,06113 PRE~FLUORINATION Po = 0,08458 Up = 1.904 NoF Up = 1,904 o
BR = 0.8 Th = 35.05 ‘szoucs Th = 25.05 . FLUORINATION U, = 2.638 o] assotrmion Uy = 2.838 . COLe
3‘ . ig&g :: kp/d wr % 1203;“ kg/d wt % ~ 500°C UFg = 4.22 ko/d 100-400°C UFg = 4,22 kg/d -50%C
-n: = 52,000 kg UF, = 375 3,4 UF, = 376 3.65 :
& ¢+ ThFy =46.54 45,2 ThF, = 46.54 45.22 t
ppts g UF. .62 3170 urd 3262 3170 Fp = 0.462 ko/d :
BaFy = 1999 19.43 BeFy = 19.99 19,42 : - ‘
W~ W Up = 1.904
33.98 1/d . U = 2.838
v / Vv = 33.98 I/d s =422
Y] ) d ¥
Uy = 2.498 . kg/!
U, = 343 FUEL Up = 1.957 _ Up = 1.957 CYLINDER
Th = 37.11 MAKE UP Lo U, = 2,89 . REDUCTION _ U, = 2.89 COLLECTION
kg/d wt % - UF, = 2.83 kg/d UFg —UFy | UF, = 4.30 kg/d L ~90%C
kp/d % 1200°F 4 o/ 6 6 o/ 4 plo
UF, = 0.71 0.0 _
é, =49.27 4802 A -
UF= 3262 .7 kg/d . L......
BeF., = 19.99 19.48 W = ‘ Hy = 0.0248 ko/df
2 _ A = 054 .
Yoze~ ™ =370
v = 23.98 I/d kg/d wt %
UFg = 4548 427
Thiy = 49.27 4630
UF = 3262 20.65
Bef, = 19.99 1878
™
ke/d :
d : ke _
Po-223 Uy = 0,05252 vV =33,98 1/d -
Pa = 0.05458 DECAY Pa = 0.002063 coLp .
Th = 35,08 o stosace Th = 35,05 FLUORINATION o TRAP : Up = 0.05252 kg/d
- k ~ : -
, bl w% 130 DAYS k/d wt% 500°C -s0°C UF, = 0.0762 ko/d
ThF, = 4654 44,60 1200°F UFy = 0.0696 0,067
LF= 32.42 3126 ThFy =48.54 44.57 kg/d
BaFp = 19.99 19.16 LIF = 3262 3124 . WASTE
NoF = 52 4,98 Befp =19.99 1914 I Pa = 0,002063 . STORAGE PERMANENT
Ty - Nef = 52 498 Th = 35.05 IN CANAL » WASTE
V = 35.84 1/d a2 kg/d wt% FP DECAY _ STORAGE
b Vv = 35.84 i/d ) © T ThE, = 4654 44.60 1000 DAYS ' -
: : Lf = 3262 312 200-500%
::? - 1999 19,18
= 52 498
£y = 0.00856 kg/d vorE
V=248 I/d
Fig. 3.1 Molten Salt -Convérter Reactor. Process Flowsheet fo;:' al.2 ':E't3 /day Fluoride Volatility Plant.
FISSION
UNCLASSIFIED
ORNL-LR-DWG 65585 R1
Uf = fissionable uranium
Uy = total uranium (includes fissionable and non-fissionable species)