-
Notifications
You must be signed in to change notification settings - Fork 10
/
ORNL-TM-2712.txt
3339 lines (2298 loc) · 104 KB
/
ORNL-TM-2712.txt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
892
893
894
895
896
897
898
899
900
901
902
903
904
905
906
907
908
909
910
911
912
913
914
915
916
917
918
919
920
921
922
923
924
925
926
927
928
929
930
931
932
933
934
935
936
937
938
939
940
941
942
943
944
945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
ORNL-TM-2712
Contract No. W-T405-eng-26
Reactor Division
FEASIBILITY STUDY OF REMOTE CUTTING AND WELDING
FOR NUCLEAR PLANT MAINTENANCE
Peter P. Holz
- LEGAL NOTICE
This Teport was prepared ag an account of Government spomsored work. Neither the United
States, nor the Commission, nor any persan acting on behalf of the Commission:
A, MaKes any warranty or reprcsn.nuticn.pxpr.:sued or implied, with reapect @ the acou-
racy, complieteness, oF usefulness of the fnfurmation contained io this report, or vhat the use
of any information, apparatus, methed, or process dlsclosed In this report may not infringe
privately owned rights; or
B. Assumes any liabilities with respect to the use «of, or for damagea resulting from the
use of any {aformatian, apparatus, method, OF Process disclosed in this report.
Au used in the above, ‘‘persen acting on bepalf of the Commission" includes any em-
ployee or cantractor of the Commission, ar ampiovee ol such contractor, o the extent that
guch employee or rontractor of the Commission, or ¢mployee of such contraclor prepires,
disseminates, T provides access to, any information pursaant o his employment oT contract
with the Cemmissgion, or his employment with such contracior,
e ————————
NOVEMBER 1969
OAK RIDGE NATIONAL LABORATORY
Oak Ridge, Tennessee
cperated by
UNION CARBIDE CORPORATION
for the
U.S. ATOMIC ENERGY COMMISSION
DISTRLI TN o D
LT UNLTMOTED
1ii
CONTENTS
ABSTRACT .
ACKNOWLEDGMENTS .
SECTION A
1. MAINTENANCE PHILOSOPHY .
1.1 Introduction .
1.2 Approaches to Maintenance.
l.2.1 Some Examples of Maintenance Methods.
1.3 Remote Maintenance Considerations.
1.3.1 Eguipment Location for Maintenance.
l.3.2 Mechanical Joint Consideraticns .
1.3.3 Welded Joint Closure Considerations .
2. HISTORY OF REMOTE WELDING .
2.1 Background .
2.2 The Pennsylvania Advanced Reactor Program.
2.3 The Atomics International Program.
2.4 State of the Art Survey .
2.5 Survey Findings-
2.6 Continued Need for Remote Welding Development.
3. THE SELECTION OF A SYSTEM TO BE DEVELOPED FOR
REMOTE MAINTENANCE. C e e e e e e e
3.1 "Orbital-Vehicle'" System Advantages.
3.2 Future System Expansion and Modification Plans .
3.2.1 Development of Additional Modules .
3.2.2 Alternate Carriage for Seal-Weld Capability .
3.2.35 Development of Special Features for
Nuclear System Applications .
SECTION B
4. PRESENT PROGRAM STATUS.
4.1 General.
L.2 ORNL's Prototype Automated Remote Cutting and
Welding System for 6 and 8-in. Pipes . .
L.2.1 Carriage.
4.2.2 Universal Machining Head.
-~ O O OV O W W
Moot e
H P O O O O
-
)
15
15
15
15
16
17
17
L7
18
18
iv
L.2.3 Universal Welding Heuad.
L.2.4 Welding Programmer and Control Unit
L.2.5 Power Supply.
L.2.6 Equipment Modifications for Remote Work .
MACHINING STUDIES .
5.1
5.2
5.3
5.4
D5
General.
Equipment Evaluation .
Tooling.
Machining Feeds and Speeds . . . . . . . . . . <
Machining Techniques for Slitting and Beveling Pipes;
Pipe End Preparation Requirements for Welding.
WELDING STUDIES .
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
General.
Preweld Joint Cleaning .
Joint Fitup Tolerance.
Inert Shield Gas
Electrode Configuration.
Automatic Arc Voltage Control.
Pre-Weld Positioning .
Root Pass.
Fill Passes.
6.10 Repair Welding .
SPECTAL ORBITAL EQUIPMENT MAINTENANCE REQUIREMENTS.
T.1
7.2
7-3
7.4
7.5
Carriage
7.1.L Drive Rollers .
T.1.2 1Idlers.
Electrical Items .
Milling Head .
Welding Head
General.
SECTION C
PROGRAM PROPOSAL: DEVELOPMENT OF REMOTE CUTTING, WELDING
AND INSPECTION EQUIPMENT FOR REACTOR SYSTEM MAINTENANCE .
8.1
Overall Requirements for Remote Cut/Weld Maintenance
18
25
25
28
28
28
30
30
31
L6
8.2 A Long-Range, Three-Phase Development Program for
Pipe and Vessel Maintenance. e e e
8.2.1 Phase I, The General Program.
8.2.2 Phase II, The Pipe Joint Program.
8.2.3 Phase III, The Vessel Closure Program .
bt
& & 4
FEASIBILITY STUDY OF REMOTE CUTTING AND WELDING
FOR NUCLEFAR PLANT MAINTENANCE
Peter P. Holz
ABSTRACT
When reactors and related systems require maintenance
and repairs on highly radicactive components, there is an
ilmportant need for remotely controlled equipment to remove
and replace parts of the nuclear systems. Remote cutting
and welding can be valuable technigues for component replace-
ment as well as for sealing flanges and vessel closures.
Welding offers very attractive advantages: Jjoints can be
made leaktight, joint configurations require less cell space
than flanged Jjoints; and the locations of joints can be
changed comparatively easily, if necessary.
In seeking equipment which could be adapted to remotely
controlled operation for reactor maintenance, ORNL selected
the Air Force "orbital vehicle" cut-and-weld system as
currently being most promising for further development to
meet nuclear system requirements. The concept of an orbital
vehicle equipment system for automated pipe work originated
in 1964 at the Rocket Propulsion Laboratory of the Air Force
Systems Command at Edwards Air Force Base. The development
of this system was performed in conjunction with North American
Rockwell Corporation, Los Angeles Division, who designed,
built and tested initial models. ORNL has started to modify
and adapt the orbital design for completely remote work
applications.
The orbital system includes a carriage, interchangeable
modules for machining or tungsten-arc welding, a weld programmer,
and a conventional power supply. The working unit is quite
compact, about 4 in. thick in radial dimension x 10 1/2 in.
long, designed to be clamped around a pipe.
To date, we have completed the detailed drawings for
fabrication of the prototype orbital system and have procured
all the components for initial non-nuclear tests of the
equipment. We have demonstrated the following operations
by remote control methods that were generally satisfactory:
clamping of the carriage on the pipe, cutting and beveling
with one orbital head, changing heads, and performing filler
pass welding opergtions. We noted that nearly perfect pipe
Joint preparation and alignment were required to achieve
acceptable root pass welding without the addition of weld
inserts. These requirements wesre the most difficult to
meet with the orbital equipment, and root pass welding gave
the most trouble. However, an alternate method of root pass
welding gave good results when joining surfaces were machined
to provide extra metal on one inside pipe edge and were given
a fusion welding without filler wire on the root pass. These
weldments showed full penetration and excellent, even bead
shape all the way around the pipe. In all cases, the subse-
quent filler passes were made easily and were of good quality.
Since welding variables such as travel speed, current, wire
feed rate, arc voltage, and arc control voltage all affect
weld quality, it was cbserved during the tests that weld
defects could often be detected as they occurred by noting
the pips on recorder chart traces.
The report describes factors involved in radioactive
system maintenance, summarizes some previous work on remote
maintenance development, and explains how the automated
orbital cutting and welding machinery system may overcome
problems that have been encountered in nuclear repair work.
Progress of the feasibility study to date is summarized,
including descriptions of the prototype equipment and the
results of machining and welding tests. The report describes
additional requirements for development to provide fully
remote operations and controls and proposes a long range
program for development of a complete remote maintenance
system for radicactive system equipment replacement by
cutting and welding.
ACKNOWLEDGMENTS
The author acknowledges with thanks the excellent cooperation and
assistance of the Permanent Tube Joint Technology Section of the Air
Force Rocket Propulsion lLaboratory, Alr Force Systems Command, Edwards,
California. The project engineer, Captain John L. Feldman, USAF, and
his staff, particularly Mr. Edward H. Stein and Lt. Albert B. Spencer,
USAF, all have done an outstanding job in supplying requested technical
information and data. C. Bruce Deering of the AEC's Oak Ridge Operations
Site Office provided liaison between AEC and the Air Force. Carl M.
Smith, Jr., gave invaluable day to day assistance with equipment design,
development, shakedown and checkout, and William A. Bird and Robert L.
Moore gave important help with trouble-shocting and refining of the
electronics and instrumentation. E. L. Armstrong, W. F. Cartwright,
T. Ray Housley, Dunlap Scott, G. M. Slaughter, Irving Spiewak, T. K.
Walters, and L. C. Williams provided valuable guidance and support.
Special thanks glso to W. E. Thompson for his assistance in editing
this report, and to others, unlisted for brevity, who contributed in
many ways .
SECTION A
1. MAINTENANCE PHILOSOPHY
1.1 Introduction
In the design, development, and testing of molten salt reactors at
the Ozk Ridge National Laboratory, the need for remote welding equipment
was encountered. However, the development of reactor designs which in-
clude provisions for maintenance by remote welding logically reguires
that a welding process be proven feasible before the design studies are
completed. Similarly, the capabllity for remote welding must be fully
developed before a large reactor is designed con the basis of maintenance
methods which require remote welding. The potential of remote welding
for saving time in replacing reactor system components and for producing
more reliable joints and seals was recognized, and feasibility studies
of remote welding were started as part of the Molten Salt Reactor Program.
From discussions of remote maintenance with the designers, builders, and
operators of other reactors, it has become clear that the special welding
equipment and techniques that have been devised on many occasions for
specific repalr or replacement Jobs are not generally applicable. There
is strong interest in a portable, remotely controlled welding system
that would be generally applicable in reactor maintenance and repair
work. A reliable, automated system to produce high-quality welds, even
without remote controls, would be welcomed by the reactor builders, who
report considerable difficulty in obtaining qualified welders and in
achieving acceptable weld quality on field work at the construction site.
Use of automated systmes for construction welding would also give confi-
dence and experience which would help the application of remotely control-
led units in maintenance and repair work.
The problems of maintenance and repair on reactor systems after
operation has built up the radiation levels are important and widespread--
no reactor is immune. The need for remote welding equipment has been
recognized by reactor designers, builders and operators; but, to date
there is no remote welder that can be used for general pipe and seal
welding applications, although special purpose devices have been em-
ployed for some reactor maintenance Jjobs.
Automatic welding equipment is being used today for many appli-
cations. Some of the automatic welding methods and equipment seem
well suited to development for remote welding. In particular, an auto-
mated pipe-welding apparatus developed by North American Aviation for
the Air Force showed promise for remote control applications in nuclear
reactor systems.
In all reactor systems maintenance must be performed by some method
whenever the need arises. If it could be accomplished with reliability
at reasonable cost, completely remote maintenance would be preferred,
because, it reduces personnel radiation exposures and simplifies the
problems of decontamination prior to undertaking the maintenance opera-
tions. Remote welding offers great promise for general application in
that almost any part of a reactor system which might fail can be cut out
and replaced if equipment is availuble for remote cutting and rewelding.
With first-of-a-kind reactors, i1t 1s necessary to test the designs
using mock-ups of the more complicated systems and components. If, at
this stage, the ability to perform remote maintenance can be tested on
the mock-ups, the final design can ve demonstrated to be functionally
sound and capable of being maintained. The satisfactory performance of
remote handling devices and techniques can be proved in mock-up tests,
giving increased confidence in thelir reliability and providing training
in maintenance techniques which will reduce downtime.
It is recognized that provisions for remote control removal and re-
placement of all components of a reactor system would be prohibitively
expensive. In practice, therefore, the degree of ease provided to accom-
plish remote maintenance depends upon the anticipated frequency of main-
tenance on each component. A reactor vesel designed for a 30-year
maintenance-free life will hopefully require no remote maintenance equip-
ment. Punps, valves, cold traps and other items which fail or need main-
tenance more frequently may justify rather elaborate remote control
devices to speed up and make more reliable the operations of maintenance
and replacement. If portable remote welding equipment can be proved
workable, even already-built reactors not designed for remote maintenance
may receive many of the benefits.
In October 1968, a draft of the "Code for Inservice Inspection of
Nuclear Reactor Coolant Systems” was developed under the sponsorship of
the American Society of Mechanical Engineers and the AEC. The Committee
which prepured the draft of the Code noted that "recognition was given
to the problems of examining radiocmctive areas where human access is im-
possible, and provisions are incorporated in the Code for the examination
of such areas by remote means which are not yet fully developed.” The
Code clearly shows that welds are considered to be of prime importance
amont the areas requiring inspection. The general need for remote cutting
and welding equipment which can repair flaws disclosed by the inspections
is given emphasis by the criteria speiled out in the Code.
1.2 Approaches to Maintenance
Components which failed or developed trouble after radioactivity
levels had built up have been repaired in many reactors. The methods
employed in making repairs have invariably been make-shift in terms of
equipment, techniques and procedures because standard equipment for re-
mote maintenance is not available. There seem to have been two general
approaches to reactor system maintenance: Where possible, flooding with
water has been used to provide radiation shielding while still allowing
visibility and mobility. In other cases portable or temporary shields,
usually lead, have been employed to protect workers who must enter
radiation fields. The methods have been combined at times.
1.2.1 Some Examples of Maintenance Methods
The Gas-Cooled Reactor Experiment in Idaho was floocded with water
and repaired by divers working underwater to break and remake flange
Jjoints in replacing sections of two cooling water lines. Two divers
worked 112 hours in making the repairs. No welding was involved.
Radiation exposures were about 400 to 600 mr for the workers' bodies
and about 50% more for their hands .}
Divers were also used in making repairs to the core support plate
and the fuel channels of the Big Rock Point boiling water reactor. This
work involved bolting pieces in place and not welding. Later, repair
work on the thermal shield of the same reactor was performed underwater
with long~handled tools and television viewing. At this time, the radia-
tion levels had increased, during additional reactor operation, to the
point where the use of divers again could not be considered. The under-
water maintenance operations involved some machining work and included
seal welding of all nuts and keepers.2’®
The Dresden-1 boiling water reactor experienced a number of cracks
in welds which were repaired by direct work from behind a lead shield
with a lead pipe to protect the worker's hand and arm. By having just
a small hole in the lead pipe to allow movement of the welding head,
workers were protected as much as possible during their working time
inside the radiation zone. Even so, more than 50 welders had to be
called upon so that no person would have to work in the radiation field
long enough to receive an overexposure to radiation.*’®
On the BONUS boiling water, nuclear superheat reactor, Oak Ridge
supplied a welder to work on the superheater steam piping. With some
water shielding and a lead box for the worker, welds were made directly
on the tubes.®
The boiling water reactor of the Oyster Creek Nuclear Power Plant
was found to have cracks in field welds on the tubes for the control rod
drives.’ Fortunately the cracks were discovered before the reactor had
been operated. Nevertheless a one-year delay resulted from the time re-
quired to diagnose the problem and its extent and to prepare to make the
necessary repairs, even though remote control operations were not neces-
sary. Similar cracks have been found, also before operations started,
in the boiling water reactors for the Nine-Mile Point Power Plant of
Niagara Mohawk and the Tarapur Nuclear Power Station in India. Had these
cracks not been discovered before operations started, the job of fixing
them would have involved long shut-downs.
For work on the calandria of the Sodium Graphite Reactor, Atomics
International developed a remotely controlled cutting and welding system.
Bench tests were promising for specialized welding on the SGR calandris,
which the remote welder was specifically designed to fit; however, the
reactor project was terminated and the equipment was never used in a
radiation field.®
A remote welder was rented from Atomics International to make weld
repairs on the tube-~to-tube sheet welds of the steam generator of the
Fermi sodium-cooled, fast reactor. This machine was used to make 1200
welds, taking 45 sec per tube.9’°
The Dounreay Fast Reactor developed a small leak in a sodium coolant
outlet pipe near the reactor vessel. The reactor was down for one year
to locate and repair the leak.'! The cutting of the leaking section was
done directly using a lead shield, but a special remote welding gadget
was designed and built for rewelding the pipe.lg:13 Welders received
their three months' radiation exposure limit in six hours' working time.
Problems were encountered in cbtaining skilled welders to do the job.
The Hallam sodium-graphite reactor used an automated remotely con-
trolled welder inside a hot cell to seal weld the containers for spent
fuel elements. Manipulators are used to operate the remote welding
apparatus.t®
1.3 Remote Maintenance Considerations
In general, radiocactive reactor system components are interconnected
with large pipes which must be disconnected and rejoined when components
are replaced. Also large vessel access openings must be opened for in-
spection and replacement of internals and then resealed. Flanges with
mechanical seals and remote welding are two possible methods of rejoining
pipe or closing vessel openings. Some of the considerations which affect
the choice of the approcach are given below. More detailed discussions on
weld Jjoint maintenance are included in Section B.
1.3.1 Equipment Location for Maintenance
To be best suited for remote maintenance, reactor components and
piping should be physically located so as to permit access from above
for removal and replacement operations. This, however, imposes rather
severe restrictions on layout since it virtually eliminates stacking of
equipment within a cell. Therefore, if cell space savings from stacking
of components are to be achieved, consideration must be given tQ the pre-
dicted frequency of maintenance on any specific assembly of piring and
components so that the most frequently worked-on assemblies will be placed
in the most readily accessible locations. The designer thus provides
unrestricted overhead access on a first priority basis for the components
needing maintenance on a regularly scheduled basis, and then provides
access for anticipated "trouble area' work. When this has been done,
remote methods can be employed most effectively to reduce the cost and
increase the reliability of maintenance operations.
1.3.2 Mechanical Joint Considerations
a. All reactor system Joints must be leak-tight to prevent the
outleakage of coolant and radioactivity or the in-leakage of
external gases which might contaminate the contained fluid.
Furthermore, scme of the reactor coolants become very corrosive
when exposed to atmospheric oxygen or moisture. An inert gas
buffer between the gas or liguid in the pipes and the atmosphere
is sometimes employed, at slightly higher pressure, to assure
that mechanical joints are effectively leak tight. Since this
seal is so important for the integrity of the system, the equip-
ment which maintains the overpressure must be extra reliable.
Any mechanical seal requires large forces to keep the sealing
surfaces in contact during all excursions of system tempera-
ture and pressure. As an example, the so0lid metal seals which
use rings in grooves require a certain minimum force to main-
tain the seal. Additional strength is needed to resist the
axial and bending stresses transmitted through the pipe. There
are acceptable clamping and bolting methods for providing this
strength where the Jjoint is not subjected to large thermal
stresses which deform the ring seal, or to high temperatures
which might anneal the clamps. Unfortunately, the higher
temperatures (1000 to 1500°F) of advanced reactor systems make
satisfactory bolting or clamping a difficult problem.
In high-radiation fields, the flanged joints must be operated
and maintained by remote means. There are problems of operating
bolts or bulky clamps by remote control, of removing the component
without damaging the joint, inspecting and cleaning the precision
seal surfaces, installing the polished ring undamaged, instal-
ling the new component, aligning the joint, remaking the clamp,
and leak checking the seal. Some of these problems would be
encountered in remote welding, also. When a mechanical Jjoint
leaks, the maintenance crew has a choice of repair by tightening
the joint or by replacing the ring with one plated with a soft
metal such as gold.
For replacement by welding or by flanged connections, all joints
connecting the component into the system must be in proper align-
ment before bolting or clamping. Warpage during the thermal
cycling that occurs in any plant may require awkward placement
of the Jjoint and a complicated installation sequence as the new
" component is brought into the final position. The changes in
previously established locations will require careful measure-
ment by remote means to determine the exact location of the in-
cell joint so that adjustments can be made to align the new
component. A mechanical joint does not permit much margin for
error in alignment and fitting after the component is in the
cell, whereas with a welded joint, in-cell machining of mating
surfaces could be used to correct certain misalignments.
1.3.3 Welded Joint Closure Considerations
8.
In joining pipes, welding can be used either to provide a full
strength, full penetration welded joint, or to provide a seal
around a gasketed flange joint. Most full-strength weld
closures require multi-pass welds which are difficult to make.
Yet these all-welded joints, to be leaktight, must be metal-
lurgically sound. dJoint alignment, purge gas, weld arc, and
weld metal feed variables will affect bead shapes and weld
quality. These variables are discussed in more detall in
Section B.
b. Numercus problems that are associated with the inspection of
welds are not encountered or are less severe with flanged
Joints. It is an accepted fact that welds must be thoroughly
and properly inspected to assure joint integrity. Nuclear
plant weld quality requirements exceed the specifications for
conventional steam power plants. Weld inspection techniques
must work in high radiation backgrounds which make normal
radiography impossible. Inspection equipment manipulations
must be controllable from remote locations and viewing is
possible only by indirect means. Inspecting with magnetic
fields, or charged particle beams, generally is unsuitable
to nuclear plant materials and/or conditions. Ultrasonic
inspection has shown promise, although much more must be done
to adapt ultrasonic techniques to remote work. The Pacific
Northwest Laboratory has proposed an ultrasconic inspection
development program for the FFTF. Another ultrasonic lnspec-
tion development program is bteing sponsored by industry
through the Ediscon Electric Institute, and is being conducted
under subcontract at the Southwest Research Institute, Houston,
Texas.>®
c. Preweld Jjoint preparation required for remote welding involves
accurate, axially square precutting of the Jjoint, matching of
the respective inside and outside diameters along with pre-
cision alignment of the pipe stub to be welded, and possible
rebeveling to obtain acceptable alignment of mating Jjoint
members. It is imperative that a thorough cleaning of the
pipe interior at the Jjoint area precede all work, and that
utmost care be taken to completely remove all weld preparation
cuttings which might damage pumps, valves, etc., 1f allowed to
remgin in the system and circulate with the fluid. Wire brushing
and solvent cleaning may also be required to prepare the weld
areas,.
d. Repairs to faulty reweld joints are equally difficult. The
previously described inspection and cleaning requirements
apply to rewelding also.
REFERENCES
Divers Repair GCRE Vessel, Nucleonics, p. T8, May 1961.
J. I. Riesland and E. A. Gustafscn (GE - San Jose), Work Performed
on Fuel Channels and the Core Support Plate at Big Rock Point
Nuclear Power Plant, Conference on Reactor Operating Experience,
July 28-29, 1965, Supplement to Vol. 8, Transactions of the
American Nuclear Society, 1965.
10.
11.
12.
13.
1k,
15.
L. M. Hausler and R. L. Hauter (Consumers Power), In-Vessel
Modifications of Irradiated Reactor Internals at Big Rock Point,
Conference on Reactor Operating Experience, July 28-29, 1965,
Supplement to Vol. 8, Transactions of the American Nuclear Society,
1965.
R. H. Holyoak (Commonwealth Edison) The 1967 In-Service Inspection
of Dresden 1 Nuclear Power Plant, Transactions of the American
Nuclear Society, Vol. 10, p. 635, November 1967.
Clifford Zitek, Personal communication during a visit to ORNL, 1968.
Everett Rogers (Osk Ridge Y-12 Plant) Personal communication;
Rogers did the welding for the BONUS repairs, 1968.
United States Atomic Energy Commission Licensing Docket No. 50-219,
Amendment 35, Final Report on Reactor Vessel Repair Program, March 1968.
L. Newcomb, Calandria Remote Maintenance Tool Development, Atomics
International Report NAA-SR-11202, April 1966.
J. F. McCarthy, Compilation of Current Technical Experience at the
Enrico Fermi Atomic Power Plant, Monthly Report No. 7 to the U. S.
Atomic Energy Commission, February 1967.
L. T. Bogarty, Modular Steam Generator Fabrication, Atomics Inter-
national Report NAA-SR-11739, February 1966.
Dounreay Developments: Good progress on PFR; DFR is back at full
power, Nuclear Engineering, p. 633, August 1968.
Memo to Myron B. Kratzer, Assistant General Manager International
Activities, U. S. AEC, from Carl R. Malmstrom, AEC Scientific Re-
presentative, U. S. Embassy, London, England; Trip Report to Dounreay,
February 20, 1968.
R. R. Matthews and K. J. Henry, Dounreay Experimental Reactor
Establishment, TRG Report 185L4R, Nuclear Engineering, Vol. 13,
No. 149, pp. 8L0-844, October 1968.
S. Berger et al., Six Element Irradiated Fuel Shipping Cask, Atomics
International Report NAA-SR-12547, Appendix 10, pages 310-319,
November 1967.
Grady Whitman, Welding Research Council, Pressure Vessel Research
Committee, Personal communication, September 1968.
2. HISTORY OF REMOTE WELDING
2.1 Background
Attempts to develop autcomated remote welding systems for use in
nuclear work have been pursued, off and on, for more than ten years.
Most of the efforts, including some at ORNL, were on a small scale.
Limited findings from the earliest remote welding work formed the
background for the Pennsylvania Advanced Reactor (PAR) maintenance
welding development program.
2.2 The Pennsylvania Advanced Reactor Program
The Pennsylvania Advanced Reactor (PAR) was planned in the mid
1950's to use a circulating aqueous slurry fuel pressurized to 1000
psi. The high-pressure system required extra care in fabrication to
avoid leaks and also placed a premium on being able to repair leaks
that developed. It was recognized that circulating fuel would increase
the radiation levels in the reactor system areas and would make com-
pletely remote maintenance a necessity.
In planning the PAR,16 Westinghouse specified remote welding as
the mandatory method for performing maintenance on the reactor plant.
Although certain phases of the development program were completed,
the PAR proJject was terminated before the remote welding technigues
were ever demonstrated in an operating reactor system. A tube-plugging
procedure had been devised to use remote welding in maintaining the
system generator; the plug was to be inserted into the tube and welded
to the tube sheet. A flange on the plug provided the metal for the
weld and alsc covered the leak path between the tube and tube sheet.
The tungsten-arc welding process was selected by the PAR group for
remotely butt welding joints in the fixed piping. To¢ simplify equipment,
it was decided that each remote welding head would be designed to fit no
more than two pipe sizes. A contract had been negotiated with a manu-
facturer of welding equipment to improve an existing machine to permit
continuous rotation welding with 100 percent arc time, with automatic
and complete control, and with completely dependable weld guality. A
prototype model of the machine with fully automatic controls showed
promise in bench tests, but it was not equipped for remote work. Also,
the machine needed further development to be sufficiently reliable for
remote maintenance work.
2.3 The Atomics International Program
During the 1960's, Atomics Internaticnal, now a Division of North
American Rockwell Corporation, developed and perfected a number of auto-
mated welding systems. Some were remctely controlled for work in con-
nection with AEC's sodium-cooled reactors; others were automated, but
not remotely controlled, for space program reguirements and for the
shop fabrication of heat exchangers and tubing systems for civilian
power reactors. While much of their work was concentrated on production
11
welding operations in shop fabrication, AI also developed advanced
remote welding technology for specific applications, such as internal
tube welding for steam generator fabrication, deep-hole welding for
work on the calandria of the sodium-~graphite reactor, and seal welding
the containers for nuclear fuel canning.
Internal welding equipment makes tube-to-tube-sheet welds and also
tube-to-tube welds, with the welding head located inside the tube. AIl's
automatically programmed system was developed for fabrication of high-
temperature, high-pressure modular steam generator Joints for the Sodium
Component Test Installation. It did not operate by remote control.'®
Deep-hole welding equipment was developed as an extension of internal
welding technology to permit remote removal and replacement of process
tube and associated graphite log assemblies from the Sodium Graphite
Reactor Calandria Core. Blind cutting and TIG rewelding were accomplished
by remote control equipment reaching as far as 40 ft through a b-in.-
inside-diameter tube.®
The seal welding of spent fuel in cans was performed in a manipu-
lator cell at Hallam.'*
2.4 State of the Art Survey
Seeking information on remote maintenance equipment and techniques
that might be applicable to molten salt reactors, ORNL conducted a
survey early in 1968 to determine the state of the art. Emphasis was
placed on remote welding, which was considered to be of greatest interest
for molten salt reactor systems. OSpecific inquiries were made about all
development and applications of remotely operated, automated equipment
for reactor system maintenance and repairs. Equipment and techniques
for cutting{ beveling, welding and testing weld quality were particularly
sought out. 7 Ve specifically loocked for a utility machine that would
do cutting, beveling and welding with one set up.
2.5 Burvey Findings
The survey disclosed a few specially designed, automated welding
assemblies which were remotely controlled by manipulators. Argonne
Naticnal Laboratory has performed welding on the complex experimental
equipment inside a hot cell in this way; at Hallam, Nebraska, Atomics
International has a manipulator cell equipped for making seal welds on
containers for spent fuel elements; Aerojet Corporation at Azusa,
California, used a similar setup for canning radioisotope sources.
The Electric Boat Company at Groton, Connecticut, and the Liquid
Carbonics Company of Chicago, both Divisions of General Dynamics,
developed an automated welding system for use on shop fabrication
work, without remocte controls. In the production of components for
submarines, welding is being done increasingly by the automated
welding systems (TIG, with weld inserts for root pass). The Nav
claims time and dollar savings along with superior weld quality.>”
It was pointed out by a number of the people interviewed that, at
i2
present, no one markets automated welding machinery for field use,
although there are many applications where automated equipment would
be most valuable.
The following comments from Mr. Richard H. Freyburg, Assistant
Manager of Operations for Consolidated Edison Company of New York,
point ocut some of the reasons why reactor builders have keen interest
in automated welding equipment, even without remote controls:
"Industry can not take trained nuclear welders from site
to site for reactor construction because union restrictions
usually permit only one company welder for every 12 welders
supplied by the local union. The training program for nuclear
welders is tedious; we're lucky to get 60% of the new men
qualified. Many of those passing the nuclear welding qualifi-
cation tests are not well suited for constructicn work in other
respects. If we had reliable, relatively simple, automated
machinery for beveling and welding, we could train welders
faster to operate the automated equipment and the quality of
the welds would be better, with fewer rejections. In fact,
automated beveling and welding machines, on construction, could
be worked around the clock. We could even afford to put on an
extra man to permit coffee breaks for the operators and still
be well ahead. Furthermore, if our people gain confidence in
the automated machinery during construction of the reactor,
they will be glad to pay the price later for a more expensive,
remotely operated machine for reactor maintenance work. My
most urgent need is for a reliable, automated welder that
reduces rejections on construction field work . "+8
Maintenance and associated program and control equipment for auto-
mated welding have not yet been simplified and made rugged to the point
where such systems economically challenge manual welding for field work.
Our survey, however, revealed two automated systems which, with modi-
fications, might be useful for remote nuclear work. One is an "orbital
vehicle combination cut, bevel, weld carriage concept' developed and
tested by North American Aviation, Los Angeles, a Division of North
American Rockwell Corporation, under Air Force Contract; the other is
a combination of either Wachs (E. H. Wachs Company, Wheeling, Illinois)
or Fein (Prescott Tool Company, West Boylston, Massachusetts) pipe
cutters for cutting, plus specially automated Dyna-Surge APW Series
Systems (Liquid Carbonic Division, General Dynamics Corporation, Chicago,
Tllinois) for welding. The Dyna-Surge system technology originated at
the Electric Boat Division of the General Dynamics Corporation and was
uged for their production welding in submarine work. Dyna-Surge weld
head assemblies employ a stationary cylindrical track, clamped around
the pipe, with a geared rotating part on which the electrode holder is
mounted. Torch support and travel components are similar to equipment
marketed by AB ASEA SVETSMASKINER, the Stockholm, Sweden manufacturer
fcr special European automated weld machinery, or by Clarke, Chapman
& Co., Ltd. of England. Wachs and Fein pipe cutters are commongly used
in coal mining operations, in fabricating gas plant equipment, 1n
13
marine salvage work, and in production pre-weld pipe end shaping. A
still experimental automatic welding machine for large size overland
transmission piping only is being built by CRC-CROSE, Inc. of Houston,
Texas, and 1s now being tried out in a full scale field test on a
Coastal States Gas Producing Company pipeline in the Southwest .1®
2.6 Continued Need for Remote Welding Development
There were two full-fledged remote welding development programs
primarily associated with reactor projects, the PAR and the SGR, which
were discontinued before remote welding equipment was fully developed.
Other devices for remote welding have been built and used to perform
specific jobs in making repairs to reactor systems.
For a number of years, ORNL has used an automated, remotely
controlled welding apparatus inside a hot cell to seal radioisotope
source containers. In this case the containers are small, the job
is repetitive, and the remote welding equipment does not have to be
moved about within the cell. In general practice, reactor fuel
elements are seal welded in thin-walled containers before being placed
in the shielded carrier when they are to be shipped off site. This
seal weld 1is usually made by remotely controlied equipment in a hot
cell. Other remote welding operations have been performed at various
times and places using equipment specially adapted for the specific
Job. The state of the art seems to be that automated welding equip-
ment has been developed to a point where it is possible to adapt com-
mercially avallable equipment to the performance of specific - and, to
date, fairly simple - remote welding Jjobs.
Although automated welding is being used increasingly in shops
for a variety of applications, there are no present applications of
automated welding to nuclear reactor system components being welded
in the field. In the shop production of components for the nuclear
power systems of submarines, automated welding is being increasingly
used. Weld insert rings are used to fusion weld Naval Jjoint root
passes. The Navy reports savings in time and cost over manual welding,
and claims superior weld quality, also.
Needs for remote welding equipment have become more widespread
and actual gpplications of equipment for performing specific remote
welding jobs have become more numerous. To date, however, no one has
perfected a generally useful remote welding system, It is instructive
to consider why the equipment has not been developed to date, even
though attempts have been made, and to evaluate the prospects for
success 1f another attempt is made. The following factors seem impor-
tant:
1. Limited funding forced previous developers to resort to
crude control and programming equipment and to limit their
mechanical designs to oversimplified hardware items.
6.
17.
18.
19.
1h
2. Welding and programmed control apparatus of the past lacked
pulsed-arc and arc length regulation, integrated digital
functional controls and sclid state devices for instant
response actuation. Today's remote control capabilities
are much more sophisticated and adaptable to meeting welding
guality specifications.
3. Miniaturized components and automated welding hardware were
not available for application in the previously attempted
remote welding systems. Welding equipment systems that have
been developed recently for the National Aeronautics and
Space Administration and for advanced aircraft applications
are much superior to those that were available in the earlier
attempts to adapt equipment for remotely controlled welding
operations.
REFERENCES
Vol. IV, Peansylvania Advanced Reactor Project, Layout and Main-
tenance, Parts 1 and 2, WCAP 1104 and 1105; Westinghouse Electric
Corporation and Pennsylvania Power and Light Company, March 1959.
Memo from P. P. Holz to Distribution, A Preliminary Survey of
Remote Cutting and Welding Techniques Under Development in the
United States, MSR-68-4k4, February 20, 1968.
Richard H. Freyburg, Assistant Manager of Operations, Consolidated
Edison Company of New York, Personal communication by telephone,
October 1, 1968.
Wall Street Journal, July 8-69 issue, Page 23, Column 4, Para-
graph 5.
15
3. THE SELECTION OF A SYSTEM TO BE DEVELOPED FOR REMOTE MAINTENANCE
3.1 "Orbital-Vehicle" System Advantages
The Air Force's orbital vehicle machinery developed by North
American-Rockwell for pipe Jjoint-replacement maintenance offers a
number of advantages for cutting and rewelding nuclear piping. A
single, compact carriage propels interchangeable heads for cutting
or welding. This single setup for all phases of repair work simpli-
fies the indexing on the spot to be cut and welded and assures re-
petitive precision tool alignment. Equipment setup time savings also
result, especlally where weldment repairs might be required.
The tungsten inert gas (TIG) welding process which had been used
by the Air Force in their work with orbital machinery was also chosen
for initial tests at ORNL because it offers most promise of meeting
nuclear weld requirements. This process has several inherent charac-
teristics that are especially suitable for remote fixed-position
welding. TIG welding is a low inertia process and is relatively slow,
which makes it much easier to control and monitor for high integrity
welds. The amount of molten metal at any time is relatively small,
creating a quick-freezing puddle with sufficient surface tension to
counteract gravity. The process thus works equally well whether the
weld is going up-hill, down-hill or horizontally. The arc length of
the non-consumable electrode can be maintained more easily than that
of a consumable electrode. There is no flux or slag associated with
the process to require special interpass cleaning, although brushing
to remove the light oxide film is desirable. Filler wire is fed
directly intc the weld puddle. The metal does not have to be trans-
ferred into a molten state across an electric arc, an operation that
sometimes results in spatter and uneven bead formations. A system
with integral wire feed has the capability to complete a weld of
thicker section than can be made by autogenous welding. It alsc is
more likely to provide satisfactory crack-free weld metal of good
composition, grain size and porosity. TIG equipment can be made
compact and portable.
3.2 Future System Expansion and Modification Plans
The overall development program for an automated cut-and-weld
reactor maintenance gsystem is divided into two parts; a system feasi-