-
Notifications
You must be signed in to change notification settings - Fork 10
/
ORNL-TM-3041.txt
8489 lines (4423 loc) · 174 KB
/
ORNL-TM-3041.txt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
892
893
894
895
896
897
898
899
900
901
902
903
904
905
906
907
908
909
910
911
912
913
914
915
916
917
918
919
920
921
922
923
924
925
926
927
928
929
930
931
932
933
934
935
936
937
938
939
940
941
942
943
944
945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
Contract No, W=74-5-eng-26
Molten-Salt Reactor Program
ORNL-TM~-3041
MSRE OPERATOR TRAINING AND OPERATING TECHNIQUES
R. H. Guymon
AUGUST 1973
NOTICE
This report was prepared as an account of work
sponsoted by the United States Government. Neither
the United States nor the United States Atomic Energy
Commission, nor any of their employees, nor any of
their contractors, subcontractors, or their employees,
makes any warranty, express or implied, or assumes any
legal liability or responsibility for the accuracy, com-
pleteness or usefulness of any information, apparatus,
product or process disclosed, or represents that its use
would not infringe privately owned rights.
OAK RIDGE NATIONAL LABORATORY
Oak Ridge, Tennessee 37830
operated by
UNION CARBIDE CORPORATION
for the
U, S. ATOMIC ENERGY COMMISSION
-
-
L
=3
i
iii
CONTENTS
Chapter Page
ABSTRACT . & v v v v 4 v v 4 6 s v o o o o & o o o o o o v
ACKNOWLEDGEMNTS ¢ » * . » o . . e . . * . . * . . * . * Vi
1. INTRODUCTION . . + & v 4 &« o o o o o o o o o o o o o o & 1
2., DESCRIPTION OF THE MSRE
3. CHRONOLOGY . . +v + & & o o & o o o o s o o o
4. OPERATING PERSONNEL . . &+« v & o & o o o o
5. TRAINING . . v v 4 v ¢ o 4 o o o o o o o o o« s o o o o 13
Initial Training . . . e e e e e e 15
Precritical Training and Certlficatlon « 48 e e e 19
Prepower Training . . . . e e e e e e e e e e e e 24
Training of Chief Operators e e e e e s e s e e e e 27
Training Before 233y Startup . . . v 0 v e e e e e e 27
Other Training . « ¢« ¢ &+ ¢ ¢« ¢ o o« & o o o o o o o 28
Training of Replacements. . . . + ¢ « ¢ ¢ « « ¢ « o« & 30
Equivalence to AEC Examination . . . . . . . . . . . 30
6. OPERATION OF THE REACTOR + . v v ¢« & ¢ ¢ o« v o o o o o & 31
Planning . . . e e . s e e e e 31
Instructions to and Communlcatlons w1th Operators . . 32
Data Taking and Record Keeping. . . . . . . . . . . . 33
7. APPROVAL OF MAINTENANCE AND DESIGN CHANGES . . . . . . . 34
8. INFORMATION AVAILABLE TO OPERATORS . . « + v & « o« « + 35
Design and Operations Report. . . . « « ¢ ¢« ¢ o o« « & 35
Other REPOTES « & v v « & + o & & s o s o o o o o o 39
Drawings . . « + o« ¢ o 4 o« e 4 s 4 e e a4 e e e e e 39
Miscellaneous . + + « « o + o s+ o o & 4 2 e s s e . 39
9. RECOMMENDATIONS. . « ¢ « ¢ 4 o o o o o o « s o o s o « 40
REFERENCES . v & & ¢ ¢ o o 4« o o s o s o s s o s o o o s 51
Appendices
A. Schedule for Initial Training. . . . « « « + « ¢« « + . . 53
B. 1Instructions for Flowsheet Checkout. . . . . . . . . . . 57
C. Schedule for Precritical Training. . . « « « ¢ « &+ &+ & 59
D. Precritical Examinations e h e e s e e e e e e e e e 63
E Schedule for Pre-Power Training. . . . . . ¢« « « « .+ . . 75
F. Pre~Power Examinations . . . C v e e e e e e e e e s 77
G. Chief Operator Training Schedule t e e e e e e e e e s 79
H. Chief Operator Review Test . . + & v v ¢ + ¢ o o o o« o« 81
I. MSRE Operator's Examination — May, 1969. . . . . . . . . 83
J. Examples of Instructions and Communications. . . . . . . 99
K. Examples of the Control-Room and Building Log o s s e s 121
L. Forms Used in Making Changes . . + ¢ o ¢ o ¢ o o o « + & 131
M. Example of MSRE Daily Report . + o o ¢ o ¢ o o o o o o & 137
ORNL-TM-3041
MSRE OPERATOR TRAINING AND OPERATING TECHNIQUES
R. H. Guymon
ABSTRACT
The MSRE was a unique, fluid-fuel reactor that operated successfully
at ORNL from 1965 through 1969. MSRE operators and supervisors, mostly, -
veteran ORNL employees, were trained and examined within the Molten-Salt
Reactor Program. Formal training sessions were held at the beginning of
prenuclear testing, just before initial criticality and before the ap-
proach to power. Training of replacements and retraining of operators
was a continuing effort. This report describes the training, the infor-
mation provided for use by the operators, operations planning and adminis-
tration, and the use of procedures. Recommendations by the author (former
MSRE operations chief) conclude the report.
Keywords: #*MSRE + *®operation + *procedures + *training +
administration + communications + examinations + operators +
qualifications + reactors + startup -+ testing
vi
ACKNOWLEDGEMENTS
The author wishes to acknowledge the efforts of S, E. Beall and C. E.
Wolfe in supplying very able operating personnel and express appreciation
to the entire crew for their contributions and fine team spirit during
training and throughout the operation of the MSRE. Special thanks is due
to P. N. Haubenreich for his leadership of the project and his suggestions
on this report.
J. R. Engel and B, H, Webster deserve much of the credit for the co-
operation between operations, experimentation, and maintenance.
1. INTRODUCTION
The objective of the Molten-Salt Reactor Program was the development
of a practical breeder reactor in which the fissile and fertile materials
are incorporated in a molten mixture of fluoride salts.l! A major step in
that development was the Molten-Salt Reactor Experiment (MSRE), a 7.4-MW
reactor that operated at ORNL from 1965 through 1969. The main purpose
of the MSRE was to demonstrate that the desirable features of the molten-
salt concept could be embodied in a practical reactor that could be con-
structed and maintained without undue difficulty and one that could be
operated safely and reliably. This purpose was accomplished, as the MSRE
operated for long intervals and with a high overall availability.?s3
Among the factors contributing to the success of the MSRE were the
very thorough preparations for operation, including careful selection and
training of operating personnel, and the disciplined manner in which the
operation was planned and conducted. It is the purpose of this report to
describe these aspects of the MSRE. Only brief descriptions of the physi-
cal plant and its history are included, since these have been widely re-
ported.
2. DESCRIPTION OF THE MSRE
The MSRE was a single-region, graphite-moderated, thermal reactor
which produced heat at a rate of 7.4 MW(th). The fuel was UF, (originally
235y and later 233U) in a carrier salt of LiF-BeF,~ZrF,. At the operating
temperature of 1200°F, this salt was a liquid with good physical proper-
ties ~~ viscosity, 8 centipoise (about like kerosene); density, 135
1b/£ft3; heat capacity, 0.57 Btu/lb °F; and a very low vapor pressure .of
<0.1 mm Hg. The liquidus temperature of the fuel salt was 813°F, so the
equipment and procedures had to be designed to prevent freezing. The salt
also had to be protected from contact with air to minimize corrosion and
accumulation of oxides.
The design conditions for full-power operation are shown in the flow
diagram (Fig. 1). The general arrangement of the plant is shown in Fig. 2.
||
STACK
)
FAN
ABSOLUTE
OFF-GAS
HOLDUP
FILTERS
BLOG.
T2 VENTILATION
© FROM
==t . COOLANT
SYSTEM
PUMP I ‘ o ) LEGEND
fl.,
|
I
—;—-uu- COOL ANT
200,000 ctm
FREEZE VALVE (TYP)
MAIN
BED -
AUX.
BED -
PP
¥
WA';ER STEAM
WA'I;ER STE
ORNL-DWG 6511410
e FUEL SALT
SALY
— HELIUM COVER GAS
———— RADICACTIVE OFF -GAS
| i
SODIUM
FLUORIDE BED
Fig. 1. MSRE Flow biagram,}.
COOLANT
DRAIN
TANK
ORNL-DWG 63-1209R
j::}TREMOTE MAINTENANCE : j
— /| CONTROL. ROOM
REACTOR CONTROL
ROOM
A7
1. REACTOR VESSEL 7. RADIATOR
- - 2. HEAT EXCHANGER 8. CCOLANT DRAIN TANK
3. FUEL PUMP 9. FANS
4. FREEZE FLANGE 10. FUEL DRAIN TANKS
5. THERMAL SHIELD 11, FLUSH TANK
Lo 6. COOLANT PUMP 12. CONTAINMENT VESSEL
13. FREEZE VALVE
Fig. 2. General Arrangement of MSRE,
In the reactor primary system, the fuel salt was recirculated by a sump-
type centrifugal pump through a shell-and-tube heat exchanger and the re-
actor vessel. The heat generated in the fuel salt as it passed through
the reactor was transferred in the heat exchanger to a molten LiF-BeF;
coolant salt. The coolant salt was circulated by means of a second sump-
type pump through the heat exchanger and through the radiator where the
heat was dissipated to the atmosphere. The rate of heat removal was con-
trolied by using either one or two blowers and by adjusting doors in the
radiator air stream and dampers in a bypass stream. Drain tanks were pro-
vided for storing the fuel and coolant salts at high temperature when the
reactor was not operating. Drain and transfer lines included freeze valves,
where salt could be frozen or thawed to block or permit flow. The salts
were drained by gravity, and were transferred back to the circulating sys-
tems by pressurizing the drain tanks with helium. Electric heaters were
used to keep the salt molten in the tanks and to preheat the piping system
before filling. Diesel~powered generators provided emergency power for
heaters and salt pumps. The salt systems normally operated with the cover
gas at 5 psig.
Most of the fission products remained in solution in the fuel salt.
One class, known as "noble metals,'" deposited on graphite and metal sur-
faces. The gaseous fission product s, krypton and xenon, were removed con-
tinuously from the circulating fuel salt in the fuel pump tank. There they
transferred from the liquid to the helium cover gas and were swept out of
the tank by a small purge stream. This stream passed through holdup piping,
a filter, and long, water-cooled beds of activated carbon. The passage of
krypton and xenon through these beds required days to weeks, by which time
all the radioisotopes but the ®3Kr had decayed so that the stream could be
safely diluted with air and discharged to the atmosphere.
The fuel and coolant systems were provided with equipment for taking
samples of the molten salt while the reactor was operating at power. The
fuel sampler was also used during operation for adding small amounts of
uranium or plutonium to compensate for burnup. An array of graphite and
metal specimens at the center of the core was removed and replaced peri-
odically during shutdowns.
The negative temperature coefficient of reactivity of the fuel and
graphite moderator made nuclear control of the system very simple. How-
ever, three control rods were provided for adjusting temperature, compen-
sating for buildup of fission products, and for shutdown.
Instrumentation was installed to adequately monitor all variables and
to automatically handle any anticipated malfunctions. This, together with
collection of much data by an on-line computer, made it possible to operate
with a minimum operating crew,
Because of the fission-product activity, the fuel-salt equipment was
contained in heavily shielded cells that were kept sealed except when main-
tenance was being done with long-handled tools through openings in the cell
roof. The fuel off-gas system was also shielded and contained. Radiation
zones were established around the coolant salt system and a few other lo-
cations, but normal operation of the reactor did not require entry into
these zomnes.
Although not shown in Fig. 2, the plant included a simple processing
facility for treating full 75-ft3 batches of fuel salt with hydrogen fluo-
ride or fluorine gases. The hydrogen fluoride treatment was used for re-
moving oxide contamination from the salt as H,0 vapor; the fluorine treat-
ment, for removing the uranium as gaseous UF6.
3. CHRONOLOGY
Design of the MSRE was started in the summer of 1960. Construction
of the primary system components and modifications of an existing building
to house the MSRE began in 1962 and by mid-1964, installation of the
salt systems was completed.8
Early in the design and development of the MSRE, some of the engineers
involved were assigned to become members of the operating staff. As design
and construction progressed, these engineers made periodic reviews and in-
spections to assure that proper consideration was being given to opera-
bility. They also began writing procedures for checkout and operation of
the systems and components. The engineer who was to head the operations
staff was given the responsibility for detailed planning of the training
program, and he and the other engineers prepared the instructional material.
As indicated on Fig. 3, the initial operating staff was assembled by July,
1964 and basic operator training was started on July 6.
As construction was completed on more parts of the plant, the effort
spent on checking, calibrating, and testing increased. In late September,
operations were placed on a 24-hour, 7-day basis with four rotating-shift
crews. Flush salt was added to the fuel flush tank, coolant salt was added
to the coolant drain tank, and auxiliary equipment was put into operation.
The fuel and coolant circulating systems were filled with salt and the
plant was operated during most of January and February, 1965. The loops
were then drained to hydrofluorinate the flush salt, to load fuel carrier
salt, and to complete other preparations for zero-power nuclear operation.
During this precritical shutdown, several weeks were spent in advanced
training of the reactor operators, with emphasis on nuclear aspects, and
the administration of comprehensive certifying examinations by Molten-Salt
Reactor Program supervision.
Criticality was attained on June 1, 1965 and the zero-power nuclear
experiments were completed during that month. The reactor was then drained
for completion of shielding and containment provisions and minor modifi-
cations. During this shutdown, the operators underwent additional training
and testing with emphasis on power operation. Nuclear operation was re-
sumed in December, 1965. After some difficulties with the fuel off~gas
system were overcome, full power was attained in May, 1966. By December
of that year, the planned program of startup testing had been completed
and solutions had been found to the various problems that had arisen. As
indicated in Fig. 3, the reactor was at full power a large percentage of
the time for the remainder of the operation with 235U, which ended in
March, 1968. During the 5-month shutdown in 1968, core specimens were
changed, various maintenance was done, the flush and fuel salts were pro-
cessed to remove the uranium, and a charge of 233y fuel was added to the
fuel carrier salt. During these months, time was available for guided
self-study by the operators, and before nuclear operation was resumed, they
were reexamined.
Criticality was attained on October 2, 1968 and on October 8, USAEC
Chairman Seaborg took the reactor power to 100 kW, marking the first time
SALT IN LOOPS SALT IN LOOPS
SALT IN LOOPS
FIRST EXAM PRECRITICAL EXAM 235U CRITICALITY
PRECRITICAL ¥ PREPOWER PREPOWER
PREPARE FOR OPERATION AND ASSEMBLE CREW INITIAL TRAINING e TRAINING + TRAINING EXAM
A : CHARG et =
CHARGE FLUSH C_H“A’R“G“E"‘“
COOLANT S&\LT sézl_‘!_gT CARRIER SALT ADD FUEL TEST CONTAINMENT
—
== MODIFICATIONS AND
PROCES” FLUSHSALT COMPLETION OF CONSTRUCTIQ"
FUEL
FLUSH — — ¥
L cooLan )
J F M A M J J A S 0 N D J F M A M J J A s 0 N D
1964 1965
Low INVESTIGATE GO TO CHIEF
POWER OFF—GAS FULL MODIFICATIONS AND REMOVE REPAIR OPERATOR
TESTS PLUGGING POWER MAINTENANCE SALTPLUG MAINTENANCE SAMPLER TRAINING
T B ) R
FEsT ORE = REPAIR CORE ==
CONTAINMENT SPECIMENS = CONTAINMENT AIR LINES SPECIMENS
== B 3 =3 Q
{
{f
ORNL-DWG 73308t
POWER (MW}
N A DD
FUEL
FLUSH
COOLANT
1967
233 CRITICALITY
TESTS AND MODIFICATIONS OPERATORS ‘ MAINTENANCE & GANMMA
OFCHEMPROCESQNGPLANT EXAM TENANCE SAMMA
REERERESE, i
CORE HOCESS SALTS e e
SPECIMENS FLUSH FUEL ADD 233U FuEL
— a T g )
8
Z6
g 4
2
S
FUEL o
LUSH
COOLANT ==
Fig. 3.
Chronology of Operator Training and Reactor Operation.
that any reactor had been operated with 233y fuel. After completion of
rod-calibration and other tests, the reactor was taken to full power in
January 1969. Investigations of the effects of gas circulating with the
fuel involved revisions to permit operation of the fuel pump at reduced
speed. Power operation continued until the first of June when the loops
were drained to change the core specimen array and to make preparations
for some special expefiments. |
The remainder of the operation involved extensive sampling, gamma
scanning, and varying of operating conditions to study the distribution
of fission products and tritium. Consideration of the limited funds
available to the Molten-Salt Reactor Program, the fact that the primary
goals of the MSRE had been achieved, and the funding needs of other molten-
salt breeder development led to a decision by program management to termi-
nate the MSRE operation. Accordingly the reactor was shut down on Dec. 12,
1969 and within 2 weeks the operating staff was disbanded.
4. OPERATING PERSONNEL
The initial operating staff was comprised of four crews, each con-
sisting of two engineers and three technicians, all under the supervision
of an operations chief and assistant operations chief, and augmented by
two day-shift technicians. Long-range planning, analysis of data, mainte-
nance coordination, and design changes were handled mostly by other groups
within the MSRE QOperations Department, whose original organization is out-
lined in Fig. 4. In addition to those shown, personnel of other ORNL di-
visions such as chemical analysis groups, health physics, industrial hygiene,
metallurgy, chemistry, instrumentation, computer programming, and maintenance
forces contributed significantly to the MSRE.
After the completion of the nuclear startup tests, the shift crews
were each reduced to one engineer and three technicians. Later, after the
operation became more routine, each crew was further reduced to 3 tech=-
nicians. On day shifts or when special experiments were being run this
3-man crew was augmented by an engineer and 1 or 2 technicians.
OPERATIONS DEPT, HEAD
COORDINATOR J_-—FDESIGN LIAISON ENGR. ]
ANALYSIS CHIEF
3 ENGINEERS
1 TECHNICIAN
MAINT, COORDINATOR
CHEMIST
2 TECHNICIANS
METALLURGIST
CHEM. PROCESSING ENGR.
Fig. 4. Original MSRE Operations Organization Chart.
ORNL—DWG 67 - 6806
OPERATIONS CHIEF
ASST. OPER. CHF,
2 TECHNICIANS
SHIFT SUPERVISOR
ASST. SHIFT SUR
3 TECHNICIANS
SHIFT SUPERVISOR
ASST. SHIFT SUP.
3 TECHNICIANS
SHIFT SUPERVISOR
ASST. SHIFT SUP.
3 TECHNICIANS
SHIFT SUPERVISOR
ASST. SHIFT SUPR.
3 TECHNICIANS
10
Turnover in personnel was moderate; between July 1964 and December 1969
3 engineers and 5 technicians joined the operations group and 10 engineers
and 4 technicians left the group.
The duties of the original operating staff were as follows.
The Operations Chief was responsible for organizing and training the
operations staff., He participated in long-range planning, general policy
decisions, and safety reviews of the reactor. He (or the Assistant Opera-
tions Chief) was responsible for the execution of the daily experimental
program and decided on the course of action to be taken in case difficul-
ties prevented carrying out the planned program.
The Assistant Operations Chief, in addition to substituting for or as~
sisting the Operations Chief in the above, investigated special operational
problems encountered, reported on operational activities at planning meet~-
ings, and directly supervised the activities of the day-shift technicians.
The Operations Chief and Assistant Operations Chief were on call at all
times. There were frequent communications between them and the evening
and midnight shifts and all shifts over the weekends.
The day-shift technicians helped in special experiments, helped take
routine samples, maintained records of chemical analyses, filed other data,
maintained operating supplies including log forms, check lists, etc., and
provided vacation relief for the regular operators.
Each Shift Supervisor was responsible for coordinating and overseeing
all operations and maintenance on his shift., It was his duty to carry out
all shift instructions, to maintain an overview of the plant with special
alertness for anomalous conditions, and to keep all members of his crew in-
formed of changes in equipment, plans, or operating procedures. He was re-
quired to be especially familiar with all equipment and operations so as to
be able to react promptly and effectively to any emergency.
The Assistant Shift Supervisor assisted in the foregoing duties and
handled special tasks such as the numerous tests required during the start-
up phase of the MSRE.
The three technicians on each shift rotated through three different
assignments; building-log, control~room, and utility. The building-log
11
technician was responsible for taking all routine data except the control-
room log. During each 8-hour shift, he made 2 complete rounds of the re~
actor site and was responsible for noting any abnormalities or departures
from the recommended maximum and minimum limits shown on his log sheets.
The control-room technician took the control-room log, calculated and plot-
ted important data, and was responsible for the operation of the reactor
from the control room. He kept a written record in the console log of all
occurrences during his shift. The utility technician was responsible for
sampling and miscellaneous tests and duties as requested. Because the
three assignments were rotated, each operator had a good understanding of
the overall operation and a familiarity with each job.
In the final organization, one of the three technicians on each crew
was designated Chief Operator and assumed most of the duties of the previ-
ous shift supervisor. Candidates for Chief Operator were given additional
training and examination before being given responsibility for the shift.
Six technicians were certified as Chief Operators so that vacation relief
could be handled. An engineer was assigned as shift supervisor on the day
shift to handle the extra work assoclated with coordinating special tests
and scheduled maintenance.
The educational background and previous experience of the original
staff plus those who were later added are summarized in Fig. 5.
All of the supervisors had BS degrees or equivalent. Two were reactor
school graduates. Five had majored in chemical engineering, 2 in nuclear
engineering, 2 in mechanical engineering, and one each in electrical engi-
neering, marine engineering, electronic engineering, and chemistry. Two
of the shift supervisors came to MSRE as new hires, having just received
BS degrees in nuclear engineering. The others had a minimum of 7 years of
prior experience in design and/or development. The average period of prior
employment by Union Carbide was 13 years (including the new hires).
Most of the technicians had at least 2 years of college (average 2.6)
and a minimum of 4 years design or operating experience (average, 12) be-
fore coming to the MSRE. The average period of prior employment by Union
Carbide was 12 years.
ORNL-DWG 733087
ENGINEERS TECHNICIANS
1 2 3 4 5 5 7 8 9 10 M 12 13 1 2 3 4 5 6 7 8 a 10 11 12 13 14 15 16 17 18
7L COLLEGE ETC.
REACTOR SCHOOL
DESIGN AND CONSTRUCTION
(OTHER THAN MOLTEN SALT)
MOLTEN SALT DESIGN AND
CONSTRUCTION
DEVELOPMENT AND OPERATION
(OTHER THAN MOLTEN SALT)
MOLTEN SALT DEVELOPMENT
OPERATION OF REACTOR LOOPS
OPERATION OF OTHER REACTORS
PREPARATION FOR MSRE TRAINING
OR OQPERATION
]
21
20
19
18
17
16
15
14
13
1
1
YEARS EDUCATION OR EXPER{ENCE
O = 0w b o N