-
Notifications
You must be signed in to change notification settings - Fork 10
/
ORNL-TM-3963.txt
3273 lines (2034 loc) · 101 KB
/
ORNL-TM-3963.txt
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
892
893
894
895
896
897
898
899
900
901
902
903
904
905
906
907
908
909
910
911
912
913
914
915
916
917
918
919
920
921
922
923
924
925
926
927
928
929
930
931
932
933
934
935
936
937
938
939
940
941
942
943
944
945
946
947
948
949
950
951
952
953
954
955
956
957
958
959
960
961
962
963
964
965
966
967
968
969
970
971
972
973
974
975
976
977
978
979
980
981
982
983
984
985
986
987
988
989
990
991
992
993
994
995
996
997
998
999
1000
- ORNL-TM-3963
ZERO-POWER EXPERIMENTS WITH
233 IN THE MSRE
J. R. Engel
B. E. Prince
a7 430 OIL A8 GINZOHE
)
i
-
QISTRIBUTIOR OF TRIS BOTUNENT (S UNLIMITED
. {
S e 7
X/ -
o/l \’.'k
* [ " Ly
= _ .- IS
o oy
&
o -
OAK RIDGE NATI
OPERATED BY UNION CARBIDE CORPORATION e FOR THE U.S. ATOMIC ENERGY (OMMISSION
This report was prepared as an account of work sponsored by the United
States Government, Neither the United States nor the United States Atomic
Energy Commission, nor any of their employees, nor any of their contractors,
subcontractors, or their employees, makes any warranty, express or implied, or
assumes any legal liability or responsibility for the accuracy, completeness or
usefulness of any information, apparatus, product or process disclosed, or
represents that its use would not infringe privately owned rights,
ORNL~TM~3963
Contract No. W=7405-eng-26
REACTOR DIVISION
7FRO-POWER EXPERIMENTS WITH 2*2°U IN THE MSRE
J. R. Engel B. E. Prince
DECEMBER 1972
NOTICE
This report was prepared as an account of work
sponsored by the United States Government. Neither
the United States nor the United States Atomic Energy
Commission, nor any of their employees, nor any of
their contractors, subcontractors, or their employees,
makes any warranty, express or implied, or assumes any
tegal lizbility or responsibility for the accuracy, com-
pleteness or usefulness of any information, apparatus,
product or process disclosed, or represents that its use
would not infringe privately owned rights,
ODAK RIDGE NATIONAL LABORATORY
Oak Ridge, Tennessee 37830
operated by
UNION CARBIDE CORPORATION
for the
U.S. ATOMIC ENERGY COMMISSION
PARES A e L
IRV O e e
=D koY I JEE R
v o -
. CLi e R e
Wl el ey ) At
= n YT
I oed & Dniaa RO e
iii
TABLE OF CONTENTS
ABSTRACT . v & 4 v o+ & o s o o s o o o o s o o
FOREWORD . 4 4 o o s o 5 o o s o o s o o s o »
INTRODUCTION . ¢ & ¢ + « o o o o o o s s o s s
TEST PROGRAM . . v 4 ¢« o ¢ ¢« v ¢ o s+ o o s+ o
System Preparation . . . + « ¢« & ¢ & o o
Chronology of TeSts . « o & o o« ¢ o« o o« &
Test Procedures . . . + ¢« s o o o & o & o
Critical Experimemt . . . . . . . .
Control-Rod Calibratiom . . . . . .
Uranium Concentration Coefficient of
Temperature Coefficient of Reactivity
Effective Delayed=Neutron Fraction .
Dynamic Characteristics . . . . . .
Noise Analysis . . + « + & ¢ ¢ o o
RESULTS AND INTERPRETATIONS . . & & ¢ ¢ « o &
Critical Loading . . . v + ¢ ¢ « o o o« &
Observed « +« « « 2 ¢ o o o « s o« o =
Predicted - & a » - 2 ® - - @ . - ®
Variations in Predictions ., . . . .
Neutron Multiplication in Drain Tank . .
Control-Rod Calibrations . « « + + « .« &
Data Analysis o+ 4o v « o o o o s s
Results . & o o o o s o o o o o o o
Concentration Coefficient of Reactivity .
Temperature Coefficient of Reactivity . .
Effective Delayed Neutron Fraction . . .
Dynamics TeStS . &+ « ¢ ¢ o o o o o ¢ o
Noise Analysis . . &« 4« + o o o « o s o« &
CONCLUSIONS . & & s o s o ¢ o s o o s o o o
Reactivity
vi
W W ~ W W =
12
13
13
14
14
15
16
16
16
20
24
31
33
33
41
46
46
48
48
52
53
ZERO-POWER EXPERIMENTS WITH 223U IN THE MSRE
J. R. Engel B, E, Prince
ABSTRACT
Zero-power nuclear tests were performed in the MSRE with
U as the principal fissile isotope in October and November
1968, The initial critical loading was 1.9 + 1% lower than the
corresponding calculated value while the measured control-rod
worths, the fuel concentration coefficient, and the temperature
coefficient of reactivity were all within 77 of their predicted
values, Dynamics tests indicated good nuclear stability and
demonstrated the adequacy of the predictions and testing tech-
niques. Neutron noise associated with circulating gas bubbles
prevented measurement of the effective delayed neutron fraction
with circulating fuel. Uncertainties in the precise condition
of the reactor, as a consequence of prior operation with 235y
fuel, and a strong dependence of the neutronics calculations on
the treatment of neutron leakage prevented any refinement of
the basic nuclear data for *°°U from the experimental results.
233
Keywords: #MSRE + #*Nuclear Analysis + *Uranium-233 + *Criticality +
*Testing + #*Startup + *Experience + Neutron Physics +
Control rods + Reactivity
vi
FOREWORD
The zero~-power physics experiments with ?®?U fuel in the Molten
Salt Reactor Experiment (MSRE) were performed within a two-month period
from September to November, 1968. Prior to that time a general outline
of the test program had been published and detailed test procedures had
been developed and approved. Because the results of these tests were
required for subsequent operations, the data were promptly analyzed and
reported in a variety of internal memos and semiannual progress reports
of the MSR Program. However, since the analytical techniques and the de-
tails of their application to this reactor had been published previously,
233y zero-power tests, no single, comprehensive re-
in connection with the
port of the 2°°U tests was prepared. After the successful conclusion of
MSRE operation, it became apparent that a summary report would have some
value in bringing together the results of the individual tests and in
identifying the techniques and procedures that were applied. The report
that follows provides such a summary,
INTRODUCTION
The MSRE was first made critical with 2°°U fuel in June, 1965 and
that event was followed by a month-long series of zero-power tests. Be-
cause this was the first operation of this unique reactor and special
analytical techniques were applied to some of the data, a comprehensive
report® of those experiments was subsequently published. The reactor was
operated with the 23®°U fuel at power levels up to 7.5 MW through March,
1968, accumulating some 9000 equivalent full-power hours (EFPH). During
that time a decision was reached to extend the operation of the reactor
to include a period with *®3U as the primary fissile isotope. Accordingly
the salt charges were processed on-site by fluoride volatility in August,
235-238y pixture as UFg (ref. 2). During
1968, to remove and recover the
the next two months 35 kg of 233U fuel as UF,~LiF eutectic was added to
the fuel carrier salt. The reactor was subsequently operated until De-
cember, 1969, accumulating another 4000 EFPH. Comprehensive summaries
of the overall operating experience with the MSRE have been published
elsewhere. (See, for example, refs. 3 and 4.)
The ?°3°U loading in the MSRE was the first use of this isotope in a
molten-salt reactor and the first critical loading in any reactor capable
of producing substantial nuclear power. Thus there was considerable in-
terest in comparing the observed critical loading and reactivity coef-
ficients with predicted values. Because of the nature of the reactor and
the uncertainties resulting from the residual fission products and other
effects of prior operation, however, the experiments could not be expected
to yield more precise values for the nuclear characteristics of 2*°3U,
Nevertheless, the data were carefully analyzed and published internally
because of their direct applicability to the analysis of subsequent power
operations.
'B, E. Prince, et al., Zero-Power Physics Experiments on the Molten-
Salt Reactor Experiment, USAEC Report ORNL-4233, Feb. 1968.
?R. B. Lindauer, Processing of the MSRE Flush and Fuel Salts, USAEC
Report, ORNL-TM-2578, August, 1969.
°P. N. Haubenreich and J. R, Engel, Experience with the Molten Salt
Reactor Experiment, Nucl. Appl. & Tech., 8, 2, pp. 118-136, Feb. 1970.
“M. W, Rosenthal, et al., Recent Progress in Molten-Salt Reactor De-
velopment, Atomic Energy Review, IX, 3, pp. 601—49, (Sept, 1971).
It is the purpose of this report to present, under one cover, a
reasonably complete picture of the zero-power tests that were performed
with 233U in the MSRE. To this end, the report begins with a section
that outlines the test program and briefly describes the procedures that
were used. This is followed by a presentation and interpretation of the
results., Since the techniques for performing and analyzing the experi-
ments were essentially the same as those applied to the *°°U tests, ex-
tensive use is made of references to previously published reports for
detailed discussions of these aspects. Finally, some general conclusions
are drawn from the results of the tests.
TEST PROGRAM
The program of zero-power tests that was planned for the *°3%U
operation is described in Ref., 5, along with a general discussion of
plans for subsequent operation of the reactor. The objectives of these
tests were essentially the same as those for the initial critical loading;
i.e., to establish the actual properties of the system and to provide the
data required for proper analysis of power operation. The first step was
to establish the critical uranium concentration under the simplest at-
tainable conditions — with the fuel salt static in an isothermal core and
all three control rods withdrawn to their upper limits. This was followed
by more additions of fissile material for control-rod calibration and to
provide the excess reactivity required for operation at power. Measure-
ments of the isothermal temperature coefficient of reactivity, the fuel
concentration coefficient, and the dynamic properties of the system were
also performed.
System Preparation
235
h
The prior operation of the MSRE wit U and the condition of the
233U that was used in the reactor both imposed special considerations on
233y tests. These led to differences in detail
the performance of the
between the **°U and the *°°U tests.
The first step in preparing for the critical experiment was to re-
move as much of the original uranium mixture as possible. This was ac=~
complished by contacting first the flush salt and then the fuel salt with
fluorine in a facility especially designed and installed for that purpose
at the reactor site.® The entire charge of flush salt, containing some
6~1/2 kg of uranium, was transferred to the processing tank where it was
fluorinated for 6.6 hr to reduce its uranium concentration to 7 ppm. (The
UF¢ product that was produced was collected on NaF traps with an activity
®J. R. Engel, MSRE Design and Operations Report, Part XI~-A, Test Program
for 223U Operation, USAEC Report, ORNL~TM-2304, Sept., 1968,
°R. B. Lindauer, MSRE Design and Operations Report, Part VII, Fuel
Handling and Processing Plant, USAEC Report, ORNL-TM-907 revised,
Dec. 28, 1967.
decontamination factor near 10°.) The salt was then treated with hy-
drogen and zirconium metal to reduce to the metallic state the corrosion
products produced in fluorinationo* These were filtered’ out of the salt
as it was returned to the reactor system. The fuel salt was then treated
as a single batch with 47 hrs of fluorination required to remove 217 kg
of uranium.
In addition to removing uranium from the MSRE salts, the processing
operations also removed some of the fission products. For example Mo, I,
Te, and Sb would be completely removed, and Nb and Ru would be partly re-
moved in the fluorination step. Some of the more noble metal fission
products might have been precipitated in the reduction step but these had
probably already been plated out on reactor surfaces before the salt was
processed., One important chemical species that was practically unaffected
by the processing was the plutonium that was produced by neutron absorptions
238 235
in U during the U operation. Within the limits of analytical ac-
curacy, all of the 589 gm of Pu calculated® to have been present remained
with the salt,
After recovery of the uranium, a portion of the fuel salt was left
in the processing tank for use in a salt distillation experiment,® (Dis-
tillation has been considered as a means of separating fission products
from carrier salts in breeder reactors.) This provision, along with the
volume reduction produced by the uranium removal, would have left the in-
ventories of both the flush and fuel-carrier salts below their desired
levels. Therefore, before the processing operations were started, two
increments of salt were added to the fuel and flush tanks to compensate
for the anticipated changes.
%
This reduction step also reduced the residual uranium to metal.
’R. B. Lindauer and C. K. McGlothlan, Design, Construction and Test-
ing of a Large Molten Salt Filter, USAEC Report, ORNL-TM-2478, March 1969.
8MSR Program Semiannu. Progr. Rep., Aug. 31, 1969, ORNL-4449, pp. 98—101.
®J., R. Hightower, Jr., et al., Low-Pressure Distillation of a Portion
of the Fuel Carrier Salt from the Molten Salt Reactor Experiment, ORNL-
4577, Aug. 1971.
Although the processing operation was very effective in removing
235=2387 nixture was
uranium from the salt that was treated, some of the
left in the system. The physical configuration of the piping at the MSRE
was such that about 17 liters of salt was left in the drain tank when a
batch was transferred out for processing. Since the last material to be
processed was fuel salt, this heel contained significant amount of uranium.
(The flush-salt heel was mixed in with the fuel salt for the final trans-
fer.) This uranium residue was measured before the *3?U critical experi-
ment was begun.
The operating plans with 2°3U included a study of the ratio of cap-
tures to fissions in that nuclide in a typical MSR spectrum. This study
depended upon precise isotopic assays of the uranium as a function of
burnup and a particular initial isotopic composition was desirable for
optimum results. The compositions and anticipated amounts of the residual
238
heel and the new fuel charge were such that additional U was required.
Therefore, a separate addition of about 0.9 kg of *?°U was made before the
233
start of the U loading. This addition was also used as an isotope di-
lution measurement to evaluate the amount and isotopic composition of the
235-23%7 heel mentiomned above. (In addition, it provided an opportunity
to check out the equipment to be used in loading the %2°U.)
The high level of fission-product radiocactivity that remained in the
fuel carrier salt after the uranium recovery made it highly desirable to
keep the reactor cell closed and shielded during the 2?2°U critical experi-
ment. Consequently, the provisions in the reactor thermal shield for ex-
tra neutron detectors were inaccessible and only the normal reactor instru-
ments could be used to follow the approach to critical and the subsequent
experiments. The external neutron source, also in the thermal shield, was
equally inaccessible, so the critical experiment excluded any measurements
based on source movement. The external source was completely overshadowed
by the very intense (a-n) source inherent'® in the fuel salt so that move-
ment of the external source probably would not have been detectable. In
addition, there was a substantial (y-n) source in the fuel from fission-
product decay gammas.
‘°R, C. Steffy, Jr., Inherent Neutron Source in MSRE with Clean
233y, USAEC Report, ORNL-TM-2685, Aug. 10, 1969,
The *3°U feed material to be used in the MSRE was made available as
UO0s containing 39 kg U of the isotopic composition shown in Table 1.
This material was converted at ORNL'' to a eutectic mixture of LiF-UF,
and loaded into containers suitable for use at the reactor site. The
presence of 220 ppm of 232" .04 the fact that the material had last been
purified some 4 years prior to its use in this application made the oxide
a strong source of gamma and high-energy alpha radiation. Conversion to
the eutectic fluoride mixture then produced a strong neutron source from
(¢-n) reactions with Be, Li, and F. Because of these radiation sources,
preparation of the feed material had to be carried out in heavily shielded
equipment, as described in detail in Ref. 9. In addition, all subsequent
operations with the enriching salt required heavy shielding.
Table 1
Isotopic Composition of ?°°U Feed Material
Abundance
U Isotope (atom %)
232 0.022
233 91.49
234 7.6
235 0.7
236 0.05
238 0.14
117 M. Chandler and S. E. Bolt, Preparation of Enriching Salt
’LiF-2?3°UF, for Refueling the Molten Salt Reactor, USAEC Report, ORNL-
4371, March 1969.
*Uranium-232 decays with a 74-year half-life through 4 successive
short-lived, a—emitting daughters to 2*?Pb. Subsequent B decays of **Pb,
212p; and 2°°T1, the latter formed by a-decay of *'?Bi, produce the gamma
radiation.
23%y loading, most of the enriching salt re-
As in the case of the
quired for criticality was to be added to the fuel carrier salt in the
drain tanks. However, the original procedure — melting the enriching
salt in large furnaces atop the drain-tank cell and transfer to the drain
tanks in liquid form — could not be used because of the shielding re-
quirements. Instead, the special arrangement of the reactor portable
maintenance shield®* and the core-graphite sampling shield shown in Fig. 1
was set up to permit the insertion of cans containing up to 7 kg of
uranium as the solid eutectic directly into the drain tank.
Chronology of Tests
233U critical experiment was begun on Sept. 10,
Fuel loading for the
1968, Over the next 11 days, about 33 kg of uranium was added through the
drain tank equipment, and one 95-g capsule was added through the sampler-
enricher on the fuel pump to recheck that system. By that time the uranium
loading was within 1/2 kg of the critical value and plans called for making
all subsequent additions through the pump bowl. The progress of the ex-
periment was then interrupted to permit removal of the special equipment
from the drain-tank cell and closure and testing of the containment.
Uranium loading was resumed on Oct. 2 and initial ecriticality with *33%U
was attained on that date after the addition of 3 more capsules of uranium.
The schedule of uranium additions (23 more capsules) and various zero-power
tests continued for several weeks, ending with a reactor drain on Nov. 28.
Although the physics tests were the major activity during this period,
the operation was not devoted exclusively to those tests. Shortly after
the start of salt circulation with *23U fuel, a change was experienced in
the amount of undissolved cover gas in the primary loop and this was in-
vestigated extensively.*® Various aspects of the fuel chemistry were also
*2R. Blumberg and E, C. Hise, MSRE Design and Operations Report, Part
X, Maintenance Equipment and Procedures, USAEC Report, ORNL-TM-910, June 1968.
*®J. R. Engel, P. N. Haubenreich, and A. Houtzeel, Spray, Mist, Bubbles,
and Foam in the Molten Salt Reactor Experiment, USAEC Report, ORNL-TM-3027,
June 1970.
ORNL-DWG 68-967R
il —~-—— ENRICHING SALT
1 TRANSPORT CASK
~ CORE GRAPHITE SAMPLING
/ SHIELD
PURGE GAS
SUPPLY -~
,f~TOOL EXTEN&ON -
SEALS
" porTABLE
MAINTENANCE SHELO Y
N
TURNTABLE AND .~ - HIGH EFFICIENCY FILTER
STORAGE WELLS —4
- EXHAUST BLOWER
CONTAINMENT ENCLOSURE ;
AND STANDPIPE ASSEMBLY = = -
[ R
| t - -FDT ACCESS FLANGE
|l . — FUEL DRAIN TANK
i (FDT)
Fig. 1. Arrangement for Adding *°°U Enriching Salt to
Fuel Drain Tank.
studied and changes were made in the oxidation-reduction potential of the
4 An unscheduled drain of the fuel loop part way through the se-
salt.
quence of tests necessitated some minor adjustments in the planned loading
program. Just before the conclusion of this phase of the operation, the
reactor power was raised briefly to 1.2 and 5.5 MW to check out the heat
rejection system,
Test Procedures
The general procedures to be followed for the various zero-power
tests were outlined in Ref. 5. In addition detailed descriptive pro-
cedures with step-by-step check lists were supplied to the reactor oper-
ators for each operation or measurement., (The analysis group responsible
for evaluating the data were on hand for consultation and to oversee the
performance of the tests, but the actual manipulations were performed by
the operating staff under the immediate direction of the operating shift
supervisors.)
Critical Experiment
233y required for initial criti-
As was indicated earlier most of the
cality was added to the fuel drain tanks using the special equipment shown
in Fig., 1. This equipment permitted the transfer of single cans of en-
riching salt (containing no more than 7 kg of U) from the shielded trans-
port cask in which they were delivered to the reactor site into the drain
tank under shielded, controlled-ventilation conditions. After the en-
riching salt had been melted out, each empty can was stored on a turntable
within the equipment for removal as a group at the end of the drain-~tank
loading operations.
The nuclear reactivity of a drain tank containing ?°?U fuel was some-
what higher than the same drain.tank containing the *?°U-*°°U mixture.
Although calculations had indicated that the drain tank would be far sub-
critical under all normal storage conditions, careful observations were
4R, E. Thoma, Chemical Aspects of MSRE Operations, USAEC Report,
ORNL-4658, Dec. 1971.
10
made during the fuel additions to ensure that criticality was not ap-
proached in the tank. To accomplish this, two neutron-sensitive cham-
bers — a sensitive BFs; chamber and a less-sensitive fission chamber to
cover a wide range of counting rates — were installed just outside the
drain tank for the loading operations, Since both (a,n) and (y-n) sources
were present in the fuel, no external source was required for neutron
monitoring.
The intense internal neutron source made counting rates with the ex~
ternal source and no fuel unreliable as a baseline in this critical ex=-
periment. Therefore, the counting rates measured during the first loop
fill with uranium-bearing salt were used as the first points on the usual
inverse-count-rate plots. Thus two loadings of predetermined size were
required before extrapolations could be made to establish the size of
subsequent loadings. The first two rounds of additions consisted of 21
and 7 kg U, respectively, and the subsequent additions were based on ex~-
trapolations of count-rate data obtained from the preceding additions with
the salt in the reactor. The objective was to bring the uranium loading
to within 1/2 kg of critical in this manner. The enriching salt was
available in cans of various sizes so that arbitrary amounts could be
added in 1/2-kg increments.
The initial charging operation required the addition of three 7-kg
cans of uranium to the fuel drain tank (FD-2). These cans were delivered
to the reactor site individually, and inserted into the charging equip-
ment. The cans were remotely suspended in the gas space of FD-2 above
the liquid carrier salt, In this position the enriching salt slowly
melted and dripped into the carrier salt below it. During this time the
can was suspended from a weighing device so that progress of the melting
could be followed. At the same time the increase in neutron count rate
was observed as the neutron source and subcritical multiplication in-
creased, After the addition, the empty can was weighed more accurately,
to ensure that it was empty, and stored on the turntable for later disposal.
Prior to the addition of each can of enriching salt, one-half of the
carrier salt was transferred to the adjacent fuel drain tank (FD-1) to
provide room in the top of the tank for suspending the cans without con-
tacting the salt. After the withdrawal of the empty can, the remaining
11
salt was returned to FD-2 for mixing and to provide neutron count-rate
data on the full tank. Extrapolations of ratios of these count rates
were used in conjunction with observations during additions to ensure that
the drain tank remained subcritical. After the addition of the first can
of enriching salt, the transfers to FD-1 also removed some uranium to keep
keff very low during subsequent additionms.
After three cans of enriching salt had been added and cross-mixed
between the drain tanks, the core and primary loop were filled with salt
to obtain the initial set of subcritical count-rate data. Filling of the
reactor vessel (the first component to fill with salt) proceeded in several
steps with count-rate data being collected at each level to verify that
the full vessel was not going to be critical. The control rods were held
in a partly withdrawn position during the fill to allow for the rapid in-
sertion of some negative reactivity and initiation of a fuel drain if
criticality should be attained prematurely. The same procedure was fol-
lowed for two subsequent additions of uranium that were made in the drain
tanks. The second addition was 7 kg of uranium in one can; the third,
5 kg in two cans. Count-rate measurements with the primary loop full
after each addition and extrapolation of the data indicated that after
the third addition, the system loading was within 500 g of the amount re-~
quired for criticality.
The remaining uranium required for criticality was added in 95-gram
increments through the sampler-enricher. (These operations were inter-
rupted for removal of the drain-tank loading equipment and sealing and
testing of the containment cell.) Each capsule was added with the fuel
salt circulating and one control rod partly inserted to prevent criti-
cality. When the contents of a capsule had been thoroughly mixed in, the
fuel pump was stopped and the control rod withdrawn to obtain neutron
counting rates. The series of data points thus obtained was used to pro-
ject the critical loading. After sufficient uranium had been added,
static criticality was established by stepwise withdrawal of the final
control rod and verified by brief operation at various nuclear power
levels up to 5 kW,
12
Control-Rod Calibration
The basic experimental procedures used to calibrate the control rods
2
350 zero-
for the #??°U loading were the same as those employed in the
power tests. In essence, data were collected at a variety of control-rod
configurations as uranium was added to establish the operating concentration.
23%y tests, we anticipated that a major
From the experience in the
source of information would be the measured differential worth of the regu-
lating rod as a function of position in the core with the other two rods
withdrawn to their upper limits. Accordingly, these measurements were made
after each of the 23 uranium enrichments that followed the attainment of
criticality in the static system, When the concentration was high enough
to allow criticality with the salt circulating, measurements were made both
in static salt and with full-flow circulation. Each measurement involved
two separate determinations of the differential worth using the rod-bump,
period technique., In this approach the reactor was first made just criti-
cal (or very slightly supercritical) at about 10 W of nuclear power by
manual adjustment of the regulating rod. The rod was then withdrawn a
short distance and the increase in power was recorded as a function of
time for about a 2-decade rise to determine the stable reactor period.
The reactor power indication from the two compensated ion chambers was
recorded digitally on magnetic tape at precisely 1l/4-sec intervals by the
on-line computer. By manually switching the amplifier gain and recording
the range with the output, a precise, unambiguous linear power record was
obtained. This approach was adopted to eliminate some of the uncertainties
associated with the extraction of period data from strip-chart records of
the output of log-count-rate meters connected to the fission chambers.
2357 tests because the on-line com-
(The latter approach was used in the
puter was not fully operational then.) In addition to the measurements
just described, two series of differential-worth data were collected with
the shim rods inserted various distances into the reactor.
Rod-drop data were collected at two points in the uranium loading
sequence, for the purpose of supplementing the differential-worth data.
In these tests the reactor integrated power (fission chamber counts ac-
cumulated on an electronic scaler) was photographed as a function of time
13
from a few seconds before a rod drop to about 30 seconds thereafter.
233 tests and described
(The technique was the same as that used in the
in Ref, 1.) The negative reactivity associated with the rod drop was
obtained by integrating the reactor kinetics equations and matching the
calculated curves to the observed data. Data were obtained for rods
dropped singly, in pairs, and as a gang of three, with the fuel salt
stationary and circulating.
Additional worth information was obtained from control-rod shadowing
measurements in which the critical position of the regulating rod was re-
corded as it was withdrawn to compensate for insertion of first one and
then both shim rods. These data were collected at 4 points in the fuel
loading sequence.
Uranium Concentration Coefficient of Reactivity
Information relating to the uranium concentration coefficient of re-
activity was accumulated throughout the zero-power tests, The only data
required were the uranium loading of the system and the critical control-
rod configuration; the latter giving the reactivity worth by way of the
rod calibration results. These data were obtained after each fuel en-
richment, both with the salt circulating and stationary.
Temperature Coefficient of Reactivity
The isothermal temperature coefficient of reactivity of the reactor
between 1175 and 1225°F was measured on two occasions before the start of
power operation with 2?°U, (The first measurement was made during the
zero-power tests themselves and the second was made at the beginning of
the next period of reactor operation.) Data were obtained for temperature
variations in both directions within this range. Each time, the tempera-
ture was varied slowly by adjusting the external heaters while critical
control-rod configurations and system temperatures were recorded with the
fuel salt circulating. At several points in each test, fuel circulation
was stopped and additional data were taken with the salt stagnant. These
measurements were subsequently judged unsatisfactory because of the ef-
fects of circulating gas bubbles in the system. A third, better determi-
nation was made later in the program when installation of a variable-
14
frequency power supply for the fuel pump made it possible to operate
the pump at reduced speed so as to circulate void-free salt.
Effective Delayed Neutron Fraction
In the %°°U zero-power tests the loss of delayed neutrons due to fuel
circulation was evaluated from reactivity changes associated with starting
and stopping the fuel pump. That determination was made possible by the
233y operation, there were no circulating voids
fact that, early in the
under normal system conditions. With the ?°°U fuel, a large reactivity
effect caused by circulating voids made this type of measurement imprac-
tical. However, some indirect data were obtained from the evaluation of
the control-rod drop tests.
Dynamic Characteristics
The zero-power dynamic characteristics of the MSRE with 223U fuel
were studied in a series of measurements of the neutron flux-to-reactivity
® Some tests were performed in which
frequency response of the system.'
single step or pulse reactivity perturbations were imposed on the reactor
at very low powers (<100 W). However, the most useful studies were those
in which the nuclear reactivity or neutron flux was perturbed in a peri-
odic manner. The periodic signals used were either pseudorandom binary
or pseudorandom ternary sequences.'® These are particular series of
square wave pulses that were chosen because they have particular charac-
teristics which permitted determination of the frequency response over a
wide spectrum with only one test. The frequency range over which we ob-
tained frequency-response results was from about 0.005 to 0.8 rad/sec.
The lower limit was set by the length of one period of the test pattern
and the high-frequency limit was determined by the time width of the
square wave pulse of shortest duration which the standard equipment would
'5R, C. Steffy, Jr., Experimental Dynamic Analysis of the MSRE with
293U Fuel, USAEC Report, ORNL-TM-2997, April 1970.
'®R. C., Steffy, Jr., Frequency-Response Testing of the Molten-Salt
Reactor Experiment, USAEC Report, ORNL-TM-2823, March 1970.
15
adequately reproduce, The shortest basic pulse width used in these tests
was 3.0 sec. The frequency range covered by these tests was essentially
the range over which thermal feedback effects are important in power
operation.
The on-line computer (Bunker-Ramo, Model 340) was programmed to
generate the sequences by opening and closing a set of relays. Voltage
was fed through the relays from an analog computer (Electronic Associates,
Inc., Model TR-10). This voltage was used to determine the movement of
the control rods, which were forced either to follow the pseudorandom test
pattern themselves or to cause the flux to follow the test pattern. The
control-rod position and the neutron flux were digitized and recorded
every 0.25 sec on magnetic tape. The data were retrieved from the tape
and stored on punched cards which could then be processed to yield the
frequency-response information.
Noise Analysis
Several sets of neutron-flux noise data were collected during the
zero-power test program with the salt stagnant and circulating. The tests
consisted simply in recording the inherent fluctuations in a neutron-flux
signal from the unperturbed reactor for subsequent analysis. Objectives
of these tests were to supplement the data on the dynamic behavior of the
reactor and to gain some information about the effective delayed-neutron
fraction. For the equivalent measurements in the ?°°U zero-power tests,
a chamber had been installed in one of the thermal-shield thimbles to ob-
tain the maximum possible sensitivity. Since these thimbles were inac-
cessible for the 2?°3U tests, the detector had to be installed in the same
facility that housed the rest of the nuclear instruments.
16
RESULTS AND INTERPRETATIONS
The zero-power tests with ?°°U established the conditions and em~
pirical information required for subsequent power operation of the reac-
tor. Comparison of observed and predicted values showed the general
validity of the calculations for the MSRE, but uncertainties in both the
calculations and the measured quantities forestalled refinement of values
for 23U nuclear characteristics. The experimental results and the sig-
nificance of any comparisons that can be made are discussed in the fol-
lowing sections,
Critical Loading
Observed
233
Most of the U required for reactor criticality was added to the
fuel salt in the drain tanks in three major steps which increased the
uranium inventory by 21, 7, and 5 kg, respectively. After each addition
neutron count-rate data were collected with the salt in the fuel loop to
follow the approach toward criticality. Since the neutron source intro-
duced into the fuel with the enriching salt was a major factor in the
count rates during the early stages of the operation, the first increment
of uranium could not by itself provide any reliable indication of the
neutron multiplication. Consequently, the first two increments of fuel
were specified on the basis of the theoretical calculations and the re-
sultant data were extrapolated to determine the size of the third.
Normally an approach to criticality is monitored by plotting an in-
verse function of observed count rates against the uranium loading. This
procedure was followed and the results from one of the neutron detectors
are shown on Fig. 2 for three different treatments of the data. For each
treatment, a straight line was drawn through the last two points and ex=-
trapolated, first toward a projected critical loading and then backward
to illustrate the deviation of the data from linearity. The solid points
are simply the inverse of the observed counting rates, an approach that
17
(x 10-2) ORNL-DWG 7212848
22 T i |
v
‘ O 1/CR