Improve pre-kickstart timelines tasks #89

Open
PeterJCLaw opened this issue Sep 27, 2023 · 0 comments
Open

Improve pre-kickstart timelines tasks #89

PeterJCLaw opened this issue Sep 27, 2023 · 0 comments
Labels
Content Relates to the content (i.e: task entries) rather than import/validation software

Comments

@PeterJCLaw
Copy link
Member

For SR2024 despite having worked out a timeline well in advance we still found that when it came to confirm spaces we hadn't actually left enough time between confirming places and wanting to send the kits out.

In future we probably need to allow:

  • Two weeks ahead of Kickstart to actually ship the kits (avoids pressure on/from our friendly courier)
  • A week before that to have confirmed the shipping details
  • A week (maybe two?) before that to be confirming places and requesting those details

We might also want to account for warming teams up a little ahead of this, so that they're (and in particular rookies are) confident we exist/what we do/etc. This should also make them more likely to respond to emails confirming their place etc.

@PeterJCLaw PeterJCLaw added the Content Relates to the content (i.e: task entries) rather than import/validation software label Sep 27, 2023
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
Content Relates to the content (i.e: task entries) rather than import/validation software
Projects
None yet
Development

No branches or pull requests

1 participant