Compare two P6 schedules exported to .xer format and report differences.
Provides an assessment of the schedule performance for the update period including:
- Performance Score - Planned progress vs actual progress for update period
- Update Period - Difference in Data Date
- Difference in Finish Date
- Difference in Must Finish By Date (if applied)
- Duration Percent Complete
- Work Percent Complete
- Cost Percent Complete (if cost loaded)
- Activity Status Table and Chart
- Activity Float Table and Chart
- Finish Constraint Trending
- Added Activities
- Deleted Activities
- Activity Name Changes
- Activity Original Duration Changes
- Activity Remaining Duration Changes
- Increased Remaining Duration
- Remaining Duration Changes when not linked to Original Duration
- Revised / Deleted Actual Dates
- Revised Calendar Assignment
- Revised WBS Assignment
- Revised Activity Type
- Added Relationships
- Deleted Relationships
- Revised Relationships
- Changes in Relationship Link (e.g FS to SS)
- Changes to Lag Duration
- Added Task Resources
- Deleted Task Resources
- Revised Budgeted Costs
- Revised Budgeted Quantities
- Added Constraints
- Deleted Constraints
- Revised Constraint Dates
- Added WBS Nodes
- Deleted WBS Nodes
- Revised WBS Names
- Added Calendars
- Deleted Calendars
- Added Non-Work Exceptions (Holidays)
- Deleted Non-Work Exceptions (Holidays)
- Added Work Exceptions (e.g. Saturday)
- Deleted Work Exceptions
- Added Task Notebook Memos
- Deleted Task Notebook Memos
- Revised Task Notebook Memos