  • The ProjectCalendaWeek methods addCalendarHours(), attachHoursToDay, removeHoursFromDay have been removed. Use addCalendarHours(day), removeCalendarHours(day) instead. (Note: this will be a breaking change if you were using the original methods to create or modify a schedule)
  • The ProjectCalendar methods attachHoursToDay and removeHoursFromDay have been removed. Use the addCalendarHours and removeCalendarHours methods instead. (Note: this will be a breaking change if you were using the original methods to create or modify a schedule)
  • The class hierarchy for ProjectCalendarHours and ProjectCalendarException has been simplified, but there should be no impact for uses of these classes.
  • The ProjectCalendarHours class now implements the List interface. Methods in this class not part ofthe List interface have been deprecated in favour of the equivalent List methods.
  • Updated MPXWriter to ensure: calendar names are quoted if necessary, all calendars have names, all calendar names are unique.
  • Updated MPXReader to recognise wk as a valid time unit.
  • Updated MPXWriter, PrimaveraPMFileWriter, SDEFWriter and PlannerWriter to ensure any working weeks defined by a calendar are represented by exceptons.
  • Updated MSPDIWriter to ensure any working weeks defined by a calendar are represented in the "legacy" exception definition used by Microsoft Project prior to 2007.
  • Updated SDEFWriter to ensure: only relevant calendars are written, and derived calendars are flattened.
  • When reading Planner schedules MPXJ will no longer create an "artificial" resource calendar for each resource. Resources will be linked directly to the calendar used in the original schedule.
  • Add suppport for reading the P6 calendar type and personal calendar flag from P6 schedules.
  • Add suppport for writing the calendar type and personal calendar flag to PMXML files.
  • Updated the calendar class hierarchy: ProjectCalendar and ProjectCalendarWeek both now inherit from a new class ProjectCalendarDays. Note that ProjectCalendar is no longer a subclass of ProjectCalendarWeek.
  • The getHours and isWorkingDay methods have been moved up to ProjectCalendar from the ProjectCalendarWeek class.
  • The ProjectCalendar method copy has been deprecated, without replacement.
  • Added a getWork method to ProjectCalendar which calculates the amount of work given a Day instance.
  • Added removeWorkWeek and removeCalendarException methods to ProjectCalendar.
  • Recurring exceptions are now added to a ProjectCalendar using the addCalendarException method which takes a recurringData instance its argument.
  • The ProjectCalendarException method setRecurringData has been removed, recurring exceptions should be added using the addCalendarExcepton method described above. (Note: this will be a breaking change if you were creating recurring exceptions)