@joniles joniles released this 23 Aug 11:42
· 835 commits to master since this release
  • Added the ResourceAssignment.getEffectiveRate method to allow the cost rate effective on a given date for a resource assignment to be calculated. For P6 schedules this will take account of the cost rate configuration included as part of the resource assignment.
  • For P6 schedules, the ResourceAssignment.getCostRateTable method now takes in account any cost rate configuration details from the resource assignment when determining which table to return.
  • A resource's Standard Rate, Overtime Rate and Cost per Use are now all derived from the resource's cost rate table, and not stored as attributes of the resource itself.
  • The resource methods setStandardRate, setOvertimeRate, and setCostPerUse have been deprecated. These attributes can now only be set or updated by modifying the resource's cost rate table.
  • When writing MPX files, only include attributes which have a non-empty, non-default value in at least one task or resource.
  • When writing MPX files, ensure attributes which have calculated values are used.
  • Add support for reading a resource assignment's rate type from P6 schedules. The rate type is accessed via the ResourceAssignment.getRateIndex method. The value returned by this method can be used to select the required rate using the CostRateTableEntry,getRate method.
  • Add support for writing a resource assignment's rate type to PMXML files.
  • Add support for reading a resource assignment's role from P6 schedules. The role is accessed via the ResourceAssignment.getRole and ResourceAssignment.setRole methods.
  • Add support for writing a resource assignment's role to PMXML files.
  • Add support for reading a resource assignment's override rate (Price / Unit) from P6 schedules. The rate is accessed via the ResourceAssignment.getOverrideRate and ResourceAssignment.setOverrideRate methods.
  • Add support for writing a resource assignment's override rate (Price / Unit) to PMXML files.
  • Add support for reading a resource assignment's rate source from P6 schedules. The rate source is accessed via the ResourceAssignment.getRateSource and ResourceAssignment.setRateSource methods.
  • Add support for writing a resource assignment's rate source to PMXML files.