- use cases -> requirements -> architecture -> implementation -> testing -> release
- Milestones:
- Use cases, Requirements (week 3)
- Feasibility, Prototype (early June)
- Implementation (end June)
- discussion on interfaces
- T2 needs: availability of resources
- main difference:
- how resources are characterized, prioriticed
- make sure data model is stable -> encapsulation
- data structure not yet defined
- interface as general as possible
- tradeoffs...
- discussion on architecture, early optimization, partitioning etc.
- note: root discussions in use cases!
- updates:
- Team 1: Ioannis, Will, Jumana
- Team 2: Vivek, Srinivas, George
- Link Collection